Difference between revisions of "NGEE Barrow 2013 Site Install Trip 2"
Jump to navigation
Jump to search
Line 24: | Line 24: | ||
* 1 AM16/32 | * 1 AM16/32 | ||
− | ===Additionally, to add to Site | + | ===Additionally, to add to Grid Site=== |
* CS106 Barometric Pressure | * CS106 Barometric Pressure | ||
− | + | ** Need to dig out a vent tube | |
+ | ** Bring up parts to put a new hole in this enclosure | ||
===Rewiring at each site=== | ===Rewiring at each site=== | ||
* Move AM16/32B #1 & #2 RES to CR1000 C1 | * Move AM16/32B #1 & #2 RES to CR1000 C1 | ||
Line 35: | Line 36: | ||
*** #3 = ID9 | *** #3 = ID9 | ||
* Also Measure Thermal Conductivity Heater Values | * Also Measure Thermal Conductivity Heater Values | ||
+ | * Bring up 3 resistors for CNR4 Thermistor measurement | ||
− | ===To Do as of | + | ===To Do as of 6/8/2013=== |
− | |||
* Wiring Diagrams | * Wiring Diagrams | ||
− | |||
* Sketch up site | * Sketch up site | ||
− | |||
− | |||
* holes in box for instrumentation maybe? | * holes in box for instrumentation maybe? | ||
− | * cut crossarms to length | + | * cut crossarms to length (in Barrow) |
− | * Change SDI-12 IDs for SR50As | + | * Change SDI-12 IDs for SR50As (in Barrow) |
− | * | + | * Copy B program additions to A & C |
− | |||
=== Remaining things to grab=== | === Remaining things to grab=== | ||
− | * | + | * Nu Rail oddball connectors from cabinet |
+ | * BP tubing for grid site | ||
+ | * Cord Grips for grid site | ||
+ | * silicone for grid site | ||
+ | |||
===To Purchase=== | ===To Purchase=== | ||
− | * | + | * More Flexible Conduit |
===Pre-trip to do=== | ===Pre-trip to do=== | ||
* Organized per site items ('''X''' means it's packed / shipped) | * Organized per site items ('''X''' means it's packed / shipped) | ||
** Precip Stand (3 sets) | ** Precip Stand (3 sets) | ||
− | *** 4 NuRail 3/4 offset cross pieces | + | *** XX 4 NuRail 3/4 offset cross pieces |
− | *** 1 Novalynx Wind Screen | + | *** XX 1 Novalynx Wind Screen |
− | *** 1 TE525m & Cable | + | *** XX 1 TE525m & Cable |
** Tripod Related | ** Tripod Related | ||
+ | *** XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS | ||
+ | *** XX 1.5" Nurail offset | ||
+ | *** XX 1" Aluminum cross arm for upper AT/RH & WS | ||
+ | *** XX HMP155s, cables, Radiation Shield | ||
+ | *** XX 014a WS, cables, nurail / cross arm mounts | ||
*** | *** | ||
− | |||
− | |||
− | |||
**** | **** | ||
**** | **** |
Revision as of 15:32, 9 June 2013
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
- Wind Screen 3x
- HMP155s 6x
- MetOne 5x
- Barometric Pressure
- Radiation Shields
- Cross Arms
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
- 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
- Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
- Net Radiometer
- NuRail Fittings for crossarms
To Add to each site
- 2 HMP155s w/ Radiation Shields
- 2 Met One WS
- 1 Tipping Bucket w/ Windscreen
- 1 CNR4 Net Radiometer with Heater/Fan Control
- 1 AM16/32
Additionally, to add to Grid Site
- CS106 Barometric Pressure
- Need to dig out a vent tube
- Bring up parts to put a new hole in this enclosure
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
- Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
- #2 = ID8
- #3 = ID9
- Reprogram the IDs for the SR50As
- Also Measure Thermal Conductivity Heater Values
- Bring up 3 resistors for CNR4 Thermistor measurement
To Do as of 6/8/2013
- Wiring Diagrams
- Sketch up site
- holes in box for instrumentation maybe?
- cut crossarms to length (in Barrow)
- Change SDI-12 IDs for SR50As (in Barrow)
- Copy B program additions to A & C
Remaining things to grab
- Nu Rail oddball connectors from cabinet
- BP tubing for grid site
- Cord Grips for grid site
- silicone for grid site
To Purchase
- More Flexible Conduit
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
- XX 1 Novalynx Wind Screen
- XX 1 TE525m & Cable
- Precip Stand (3 sets)
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
- XX 1.5" Nurail offset
- XX 1" Aluminum cross arm for upper AT/RH & WS
- XX HMP155s, cables, Radiation Shield
- XX 014a WS, cables, nurail / cross arm mounts
-
- Tripod Related
Things to buy
- Bit o' Food?
- ?
Stuff to bring
things not on a PR yet
Technical Gear
- Shotgun
- Keypads
- fish tape
- Tool Bags
- Computer & (packed) SC32B
- Climbing harness
- Serial Cables & spares
- Sawzall
- drill
Food to bring out
- Optional
Probable Luggage
- Shotgun [Bob #1]
- Bob Personal backpack [Bob #2]
- Work Actionpacker #1 [Bob #3]
Rough on-site todo
- Remove box & solar panel
- Measure from top of tripod base to cross arm... note in fieldbook
- Remove crossarm off tripod
- unscrew center pole
- put 1.5" offset nurail fitting on new center pole
- attach new center pole
- put cross arm, instrument box, and solar panel back on the tower.
- Install new instrument box on lower leg.
- Mount all new sensors
- Net Radiometer @ 1-1.5m
- WS on radiometer crossarm
- HMP155 on radiometer crossarm
- Second HMP155 & WS high up on tower, maybe as high as they'll reach.
- Armor all the cabling
- Armor and install the precip bucket.
- Install the precip wind screen
- send new program to data logger