| Line 24: | Line 24: | ||
* 1 AM16/32  | * 1 AM16/32  | ||
| − | ===Additionally, to add to Site   | + | ===Additionally, to add to Grid Site===  | 
* CS106 Barometric Pressure  | * CS106 Barometric Pressure  | ||
| − | + | ** Need to dig out a vent tube  | |
| + | ** Bring up parts to put a new hole in this enclosure  | ||
===Rewiring at each site===  | ===Rewiring at each site===  | ||
* Move AM16/32B #1 & #2 RES to CR1000 C1  | * Move AM16/32B #1 & #2 RES to CR1000 C1  | ||
| Line 35: | Line 36: | ||
*** #3 = ID9  | *** #3 = ID9  | ||
* Also Measure Thermal Conductivity Heater Values  | * Also Measure Thermal Conductivity Heater Values  | ||
| + | * Bring up 3 resistors for CNR4 Thermistor measurement  | ||
| − | ===To Do as of   | + | ===To Do as of 6/8/2013===  | 
| − | |||
* Wiring Diagrams  | * Wiring Diagrams  | ||
| − | |||
* Sketch up site  | * Sketch up site  | ||
| − | |||
| − | |||
* holes in box for instrumentation maybe?  | * holes in box for instrumentation maybe?  | ||
| − | * cut crossarms to length  | + | * cut crossarms to length (in Barrow)  | 
| − | * Change SDI-12 IDs for SR50As  | + | * Change SDI-12 IDs for SR50As (in Barrow)  | 
| − | *   | + | * Copy B program additions to A & C  | 
| − | |||
=== Remaining things to grab===  | === Remaining things to grab===  | ||
| − | *   | + | * Nu Rail oddball connectors from cabinet  | 
| + | * BP tubing for grid site  | ||
| + | * Cord Grips for grid site  | ||
| + | * silicone for grid site  | ||
| + | |||
===To Purchase===  | ===To Purchase===  | ||
| − | *   | + | * More Flexible Conduit  | 
===Pre-trip to do===  | ===Pre-trip to do===  | ||
* Organized per site items ('''X''' means it's packed / shipped)  | * Organized per site items ('''X''' means it's packed / shipped)  | ||
** Precip Stand  (3 sets)  | ** Precip Stand  (3 sets)  | ||
| − | *** 4 NuRail 3/4 offset cross pieces  | + | *** XX 4 NuRail 3/4 offset cross pieces  | 
| − | *** 1 Novalynx Wind Screen  | + | *** XX 1 Novalynx Wind Screen  | 
| − | *** 1 TE525m & Cable  | + | *** XX 1 TE525m & Cable  | 
** Tripod Related  | ** Tripod Related  | ||
| + | *** XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS  | ||
| + | *** XX 1.5" Nurail offset  | ||
| + | *** XX 1" Aluminum cross arm for upper AT/RH & WS  | ||
| + | *** XX HMP155s, cables, Radiation Shield  | ||
| + | *** XX 014a WS, cables, nurail / cross arm mounts  | ||
***    | ***    | ||
| − | |||
| − | |||
| − | |||
****    | ****    | ||
****    | ****    | ||
Revision as of 15:32, 9 June 2013
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
 - Wind Screen 3x
 - HMP155s 6x
 - MetOne 5x
 - Barometric Pressure
 - Radiation Shields
 - Cross Arms
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
 - 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
 
 - Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
 
 - Net Radiometer
 - NuRail Fittings for crossarms
 
 
To Add to each site
- 2 HMP155s w/ Radiation Shields
 - 2 Met One WS
 - 1 Tipping Bucket w/ Windscreen
 - 1 CNR4 Net Radiometer with Heater/Fan Control
 - 1 AM16/32
 
Additionally, to add to Grid Site
- CS106 Barometric Pressure
- Need to dig out a vent tube
 - Bring up parts to put a new hole in this enclosure
 
 
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
 - Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
 - #2 = ID8
 - #3 = ID9
 
 
 - Reprogram the IDs for the SR50As
 - Also Measure Thermal Conductivity Heater Values
 - Bring up 3 resistors for CNR4 Thermistor measurement
 
To Do as of 6/8/2013
- Wiring Diagrams
 - Sketch up site
 - holes in box for instrumentation maybe?
 - cut crossarms to length (in Barrow)
 - Change SDI-12 IDs for SR50As (in Barrow)
 - Copy B program additions to A & C
 
Remaining things to grab
- Nu Rail oddball connectors from cabinet
 - BP tubing for grid site
 - Cord Grips for grid site
 - silicone for grid site
 
To Purchase
- More Flexible Conduit
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand  (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
 - XX 1 Novalynx Wind Screen
 - XX 1 TE525m & Cable
 
 
 - Precip Stand  (3 sets)
 
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
 - XX 1.5" Nurail offset
 - XX 1" Aluminum cross arm for upper AT/RH & WS
 - XX HMP155s, cables, Radiation Shield
 - XX 014a WS, cables, nurail / cross arm mounts
 - 
 
 
- Tripod Related
 
Things to buy
- Bit o' Food?
 - ?
 
Stuff to bring
things not on a PR yet
Technical Gear
- Shotgun
 - Keypads
 - fish tape
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Serial Cables & spares
 - Sawzall
 - drill
 
Food to bring out
- Optional
 
Probable Luggage
- Shotgun [Bob #1]
 - Bob Personal backpack [Bob #2]
 - Work Actionpacker #1 [Bob #3]
 
Rough on-site todo
- Remove box & solar panel
 - Measure from top of tripod base to cross arm... note in fieldbook
 - Remove crossarm off tripod
 - unscrew center pole
 - put 1.5" offset nurail fitting on new center pole
 - attach new center pole
 - put cross arm, instrument box, and solar panel back on the tower.
 - Install new instrument box on lower leg.
 - Mount all new sensors
- Net Radiometer @ 1-1.5m
 - WS on radiometer crossarm
 - HMP155 on radiometer crossarm
 - Second HMP155 & WS high up on tower, maybe as high as they'll reach.
 - Armor all the cabling
 - Armor and install the precip bucket.
 - Install the precip wind screen
 
 - send new program to data logger