=== Remaining things to grab===  | === Remaining things to grab===  | ||
| − | * Nu Rail oddball connectors from cabinet  | + | * XXX Nu Rail oddball connectors from cabinet  | 
* BP tubing for grid site  | * BP tubing for grid site  | ||
| − | * Cord Grips for grid site  | + | * '''Cord Grips for grid site'''  | 
* silicone for grid site  | * silicone for grid site  | ||
| Line 57: | Line 57: | ||
===To Purchase===  | ===To Purchase===  | ||
* More Flexible Conduit  | * More Flexible Conduit  | ||
| + | * Vent Tube  | ||
===Pre-trip to do===  | ===Pre-trip to do===  | ||
| Line 81: | Line 82: | ||
===Things to buy===  | ===Things to buy===  | ||
* Bit o' Food?  | * Bit o' Food?  | ||
| − | *   | + | * 1.5" Pipe Threader  | 
| + | * Flex Conduit  | ||
===Stuff to bring===  | ===Stuff to bring===  | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
==== Technical Gear ====  | ==== Technical Gear ====  | ||
| − | |||
* Keypads  | * Keypads  | ||
| − | *   | + | * XX fish tape  | 
* Tool Bags    | * Tool Bags    | ||
* Computer & (packed) SC32B    | * Computer & (packed) SC32B    | ||
* Climbing harness  | * Climbing harness  | ||
* Serial Cables & spares  | * Serial Cables & spares  | ||
| − | * Sawzall  | + | * XX Sawzall  | 
| − | * drill  | + | * XX drill  | 
| + | * Pipe Wrench  | ||
| + | * 1.5" Pipe Threader  | ||
==== Food to bring out ====  | ==== Food to bring out ====  | ||
* Optional  | * Optional  | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | ====Rough on-site todo====  | + | ====Rough on-site todo (for each site)====  | 
| − | |||
# Measure from top of tripod base to cross arm... note in fieldbook  | # Measure from top of tripod base to cross arm... note in fieldbook  | ||
| − | # Remove crossarm off tripod  | + | # Remove box & solar panel from tripod mast  | 
| + | # Remove existing crossarm off tripod  | ||
# unscrew center pole  | # unscrew center pole  | ||
# put 1.5" offset nurail fitting on new center pole  | # put 1.5" offset nurail fitting on new center pole  | ||
| − | #   | + | # add top of tower cross arm with anemometer & HMP155  | 
| − | # put cross arm, instrument box, and solar panel back on the tower  | + | ## Armor and secure these two cables  | 
| − | + | # screw on the new center pole  | |
| + | # put the existing cross arm, instrument box, and solar panel back on the tower.  | ||
# Mount all new sensors  | # Mount all new sensors  | ||
| − | ##   | + | ## On lowest crossarm, 1-1.5m above ground surface  | 
| − | ##   | + | ### Net Radiometer  | 
| − | ##   | + | ### Cross Arm bracket  | 
| − | ##   | + | #### Wind Speed   | 
| − | ## Armor all the cabling  | + | ### HMP155 on radiometer crossarm  | 
| + | ## Armor all the cabling lower cabling  | ||
## Armor and install the precip bucket.  | ## Armor and install the precip bucket.  | ||
## Install the precip wind screen  | ## Install the precip wind screen  | ||
# send new program to data logger  | # send new program to data logger  | ||
| + | |||
| + | ====Idealized Rough Itinerary (with dates to float depending on how long things take)====  | ||
| + | I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.<br>  | ||
| + | 6/11  | ||
| + | * Fly to Barrow  | ||
| + | * Sort Shipped Gear  | ||
| + | * Track down a sled  | ||
| + | * Organize stuff locally in Barrow  | ||
| + | * Quick trip to the sites if there is time  | ||
| + | * Look at D site box for parts (and prepare for shipment back to Fairbanks)  | ||
| + | 6/12  | ||
| + | * Haul stuff out for A site  | ||
| + | * Add components to A site  | ||
| + | 6/13  | ||
| + | * Haul stuff out for B site  | ||
| + | * Finish A site  | ||
| + | * Start B site  | ||
| + | 6/14  | ||
| + | * Haul stuff out for C site  | ||
| + | * Finish B site  | ||
| + | * Start C site?  | ||
| + | 6/15  | ||
| + | * Finish C site  | ||
| + | 6/16  | ||
| + | * Ship stuff back to Fairbanks  | ||
| + | * Depart for Fairbanks  | ||
Revision as of 10:53, 10 June 2013
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
 - Wind Screen 3x
 - HMP155s 6x
 - MetOne 5x
 - Barometric Pressure
 - Radiation Shields
 - Cross Arms
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
 - 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
 
 - Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
 
 - Net Radiometer
 - NuRail Fittings for crossarms
 
 
To Add to each site
- 2 HMP155s w/ Radiation Shields
 - 2 Met One WS
 - 1 Tipping Bucket w/ Windscreen
 - 1 CNR4 Net Radiometer with Heater/Fan Control
 - 1 AM16/32
 
Additionally, to add to Grid Site
- CS106 Barometric Pressure
- Need to dig out a vent tube
 - Bring up parts to put a new hole in this enclosure
 
 
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
 - Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
 - #2 = ID8
 - #3 = ID9
 
 
 - Reprogram the IDs for the SR50As
 - Also Measure Thermal Conductivity Heater Values
 - Bring up 3 resistors for CNR4 Thermistor measurement
 
To Do as of 6/8/2013
- Wiring Diagrams
 - Sketch up site
 - holes in box for instrumentation maybe?
 - cut crossarms to length (in Barrow)
 - Change SDI-12 IDs for SR50As (in Barrow)
 - Copy B program additions to A & C
 
Remaining things to grab
- XXX Nu Rail oddball connectors from cabinet
 - BP tubing for grid site
 - Cord Grips for grid site
 - silicone for grid site
 
To Purchase
- More Flexible Conduit
 - Vent Tube
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand  (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
 - XX 1 Novalynx Wind Screen
 - XX 1 TE525m & Cable
 
 
 - Precip Stand  (3 sets)
 
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
 - XX 1.5" Nurail offset
 - XX 1" Aluminum cross arm for upper AT/RH & WS
 - XX HMP155s, cables, Radiation Shield
 - XX 014a WS, cables, nurail / cross arm mounts
 - 
 
 
- Tripod Related
 
Things to buy
- Bit o' Food?
 - 1.5" Pipe Threader
 - Flex Conduit
 
Stuff to bring
Technical Gear
- Keypads
 - XX fish tape
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Serial Cables & spares
 - XX Sawzall
 - XX drill
 - Pipe Wrench
 - 1.5" Pipe Threader
 
Food to bring out
- Optional
 
Rough on-site todo (for each site)
- Measure from top of tripod base to cross arm... note in fieldbook
 - Remove box & solar panel from tripod mast
 - Remove existing crossarm off tripod
 - unscrew center pole
 - put 1.5" offset nurail fitting on new center pole
 - add top of tower cross arm with anemometer & HMP155
- Armor and secure these two cables
 
 - screw on the new center pole
 - put the existing cross arm, instrument box, and solar panel back on the tower.
 - Mount all new sensors
- On lowest crossarm, 1-1.5m above ground surface
- Net Radiometer
 - Cross Arm bracket
- Wind Speed
 
 - HMP155 on radiometer crossarm
 
 - Armor all the cabling lower cabling
 - Armor and install the precip bucket.
 - Install the precip wind screen
 
 - On lowest crossarm, 1-1.5m above ground surface
 - send new program to data logger
 
Idealized Rough Itinerary (with dates to float depending on how long things take)
I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.
6/11
- Fly to Barrow
 - Sort Shipped Gear
 - Track down a sled
 - Organize stuff locally in Barrow
 - Quick trip to the sites if there is time
 - Look at D site box for parts (and prepare for shipment back to Fairbanks)
 
6/12
- Haul stuff out for A site
 - Add components to A site
 
6/13
- Haul stuff out for B site
 - Finish A site
 - Start B site
 
6/14
- Haul stuff out for C site
 - Finish B site
 - Start C site?
 
6/15
- Finish C site
 
6/16
- Ship stuff back to Fairbanks
 - Depart for Fairbanks