Difference between revisions of "NGEE Barrow 2013 Site Install Trip 2"
Jump to navigation
Jump to search
(4 intermediate revisions by 2 users not shown) | |||
Line 6: | Line 6: | ||
** Wind Screen 3x | ** Wind Screen 3x | ||
** HMP155s 6x | ** HMP155s 6x | ||
− | ** MetOne | + | ** MetOne 6x |
** Barometric Pressure | ** Barometric Pressure | ||
** Radiation Shields | ** Radiation Shields | ||
− | ** Cross Arms | + | ** Cross Arms & Mounts |
*** 1.5" Sched 40 Aluminum = Net Radiometer 3x | *** 1.5" Sched 40 Aluminum = Net Radiometer 3x | ||
*** 1" Sched 40 Aluminum = Upper WS & AT/RH 3x | *** 1" Sched 40 Aluminum = Upper WS & AT/RH 3x | ||
Line 15: | Line 15: | ||
*** 1.5" Sched 40 Galvanized Pipe | *** 1.5" Sched 40 Galvanized Pipe | ||
** Net Radiometer | ** Net Radiometer | ||
+ | *** Fan/Heater is in Barrow | ||
** NuRail Fittings for crossarms | ** NuRail Fittings for crossarms | ||
===To Add to each site=== | ===To Add to each site=== | ||
* 2 HMP155s w/ Radiation Shields | * 2 HMP155s w/ Radiation Shields | ||
− | * 2 Met One WS | + | * 1 pcs 107 radiation shield (bringing it, will mull when looking at as-built. |
+ | * 2 Met One 014a WS | ||
+ | * 3pcs Cross Arm Mounts for each | ||
+ | ** 3.5m cross arm | ||
+ | ** 3.5m WS | ||
+ | ** 1m WS | ||
* 1 Tipping Bucket w/ Windscreen | * 1 Tipping Bucket w/ Windscreen | ||
+ | ** Some alter-shield NuRail fittings are on site. Check the battery box I think?... also may have been repurposed for snow sensors, my notes are unclear. Also check the D site box in storage. | ||
* 1 CNR4 Net Radiometer with Heater/Fan Control | * 1 CNR4 Net Radiometer with Heater/Fan Control | ||
− | * 1 AM16/ | + | * 1 AM16/32B inside the box |
+ | * Cable Management inside the box (new cable list:) | ||
+ | ** 2 pcs 014a | ||
+ | ** 2 pcs hmp155 | ||
+ | ** 3 pcs cnr4 | ||
+ | * might go looking for a short steel cable of some sort to run down the pipe. | ||
+ | * Anything else? | ||
===Additionally, to add to Grid Site=== | ===Additionally, to add to Grid Site=== | ||
− | * CS106 Barometric Pressure | + | * Maybe? Still on the fence about this due to ground location of the box. CS106 Barometric Pressure. Could also add to A yet. |
** Need to dig out a vent tube | ** Need to dig out a vent tube | ||
** Bring up parts to put a new hole in this enclosure | ** Bring up parts to put a new hole in this enclosure | ||
+ | * Finish MD485 Networking. | ||
+ | * Silicone up Grid Box new hole (md485 cable) | ||
+ | |||
===Rewiring at each site=== | ===Rewiring at each site=== | ||
* Move AM16/32B #1 & #2 RES to CR1000 C1 | * Move AM16/32B #1 & #2 RES to CR1000 C1 | ||
Line 35: | Line 51: | ||
*** #2 = ID8 | *** #2 = ID8 | ||
*** #3 = ID9 | *** #3 = ID9 | ||
− | * Also Measure Thermal Conductivity Heater Values | + | * XX Also Measure Thermal Conductivity Heater Values |
− | * Bring up 3 resistors for CNR4 Thermistor measurement | + | * XX Bring up 3 resistors for CNR4 Thermistor measurement |
===To Do as of 6/8/2013=== | ===To Do as of 6/8/2013=== | ||
* Wiring Diagrams | * Wiring Diagrams | ||
− | * Sketch up site | + | * XX Sketch up site |
* holes in box for instrumentation maybe? | * holes in box for instrumentation maybe? | ||
* cut crossarms to length (in Barrow) | * cut crossarms to length (in Barrow) | ||
Line 49: | Line 65: | ||
=== Remaining things to grab=== | === Remaining things to grab=== | ||
− | * Nu Rail oddball connectors from cabinet | + | * XXX Nu Rail oddball connectors from cabinet |
− | * BP tubing for grid site | + | * XXX BP tubing for grid site |
− | * Cord Grips for grid site | + | * XXX Cord Grips for grid site |
− | * silicone for grid site | + | * XXX silicone for grid site |
===To Purchase=== | ===To Purchase=== | ||
− | * More Flexible Conduit | + | * XXX More Flexible Conduit |
+ | * XXX Vent Tube | ||
+ | * XXX Cable Management supplies | ||
+ | * '''5/16" Washers''' | ||
+ | * '''13/16" / 3/4" drill bit''' | ||
===Pre-trip to do=== | ===Pre-trip to do=== | ||
Line 71: | Line 91: | ||
*** XX HMP155s, cables, Radiation Shield | *** XX HMP155s, cables, Radiation Shield | ||
*** XX 014a WS, cables, nurail / cross arm mounts | *** XX 014a WS, cables, nurail / cross arm mounts | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
===Things to buy=== | ===Things to buy=== | ||
− | * Bit o' Food? | + | * XXX Bit o' Food? |
− | * | + | * 1.5" Pipe Threader |
+ | * XXX Flex Conduit | ||
===Stuff to bring=== | ===Stuff to bring=== | ||
− | |||
− | |||
− | |||
− | |||
− | |||
==== Technical Gear ==== | ==== Technical Gear ==== | ||
− | * | + | * XXX Keypads |
− | + | * XXX fish tape | |
− | * | ||
* Tool Bags | * Tool Bags | ||
* Computer & (packed) SC32B | * Computer & (packed) SC32B | ||
* Climbing harness | * Climbing harness | ||
− | * Serial Cables & spares | + | * XXX Serial Cables & spares |
− | * Sawzall | + | * XXX Sawzall |
− | * drill | + | * XXX drill |
+ | * XXX Pipe Wrench | ||
+ | * 1.5" Pipe Threader | ||
==== Food to bring out ==== | ==== Food to bring out ==== | ||
* Optional | * Optional | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | ====Rough on-site todo==== | + | ====Rough on-site todo (for each site)==== |
− | |||
# Measure from top of tripod base to cross arm... note in fieldbook | # Measure from top of tripod base to cross arm... note in fieldbook | ||
− | # Remove crossarm off tripod | + | # Remove box & solar panel from tripod mast |
+ | # Remove existing crossarm off tripod | ||
# unscrew center pole | # unscrew center pole | ||
# put 1.5" offset nurail fitting on new center pole | # put 1.5" offset nurail fitting on new center pole | ||
− | # | + | # add top of tower cross arm with anemometer & HMP155 |
− | # put cross arm, instrument box, and solar panel back on the tower | + | ## Armor and secure these two cables |
− | + | # screw on the new center pole | |
+ | # put the existing cross arm, instrument box, and solar panel back on the tower. | ||
# Mount all new sensors | # Mount all new sensors | ||
− | ## | + | ## On lowest crossarm, 1-1.5m above ground surface |
− | ## | + | ### Net Radiometer |
− | ## | + | ### Cross Arm bracket |
− | ## | + | #### Wind Speed |
− | ## Armor all the cabling | + | ### HMP155 on radiometer crossarm |
+ | ## Armor all the cabling lower cabling | ||
## Armor and install the precip bucket. | ## Armor and install the precip bucket. | ||
## Install the precip wind screen | ## Install the precip wind screen | ||
# send new program to data logger | # send new program to data logger | ||
+ | ## Bring cabling into the box and wire into the appropriate data logger / multiplexer. | ||
+ | |||
+ | |||
+ | ====Idealized Rough Itinerary (with dates to float depending on how long things take)==== | ||
+ | I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.<br> | ||
+ | 6/11 | ||
+ | * Fly to Barrow | ||
+ | * Sort Shipped Gear | ||
+ | * Track down a sled | ||
+ | * Organize stuff locally in Barrow | ||
+ | * Quick trip to the sites if there is time | ||
+ | * Look at D site box for parts (and prepare for shipment back to Fairbanks) | ||
+ | 6/12 | ||
+ | * Haul stuff out for A site | ||
+ | * Add components to A site | ||
+ | 6/13 | ||
+ | * Haul stuff out for B site | ||
+ | * Finish A site | ||
+ | * Start B site | ||
+ | 6/14 | ||
+ | * Haul stuff out for C site | ||
+ | * Finish B site | ||
+ | * Start C site? | ||
+ | 6/15 | ||
+ | * Finish C site | ||
+ | 6/16 | ||
+ | * Ship stuff back to Fairbanks | ||
+ | * Depart for Fairbanks |
Latest revision as of 16:10, 10 June 2013
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
- Wind Screen 3x
- HMP155s 6x
- MetOne 6x
- Barometric Pressure
- Radiation Shields
- Cross Arms & Mounts
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
- 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
- Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
- Net Radiometer
- Fan/Heater is in Barrow
- NuRail Fittings for crossarms
To Add to each site
- 2 HMP155s w/ Radiation Shields
- 1 pcs 107 radiation shield (bringing it, will mull when looking at as-built.
- 2 Met One 014a WS
- 3pcs Cross Arm Mounts for each
- 3.5m cross arm
- 3.5m WS
- 1m WS
- 1 Tipping Bucket w/ Windscreen
- Some alter-shield NuRail fittings are on site. Check the battery box I think?... also may have been repurposed for snow sensors, my notes are unclear. Also check the D site box in storage.
- 1 CNR4 Net Radiometer with Heater/Fan Control
- 1 AM16/32B inside the box
- Cable Management inside the box (new cable list:)
- 2 pcs 014a
- 2 pcs hmp155
- 3 pcs cnr4
- might go looking for a short steel cable of some sort to run down the pipe.
- Anything else?
Additionally, to add to Grid Site
- Maybe? Still on the fence about this due to ground location of the box. CS106 Barometric Pressure. Could also add to A yet.
- Need to dig out a vent tube
- Bring up parts to put a new hole in this enclosure
- Finish MD485 Networking.
- Silicone up Grid Box new hole (md485 cable)
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
- Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
- #2 = ID8
- #3 = ID9
- Reprogram the IDs for the SR50As
- XX Also Measure Thermal Conductivity Heater Values
- XX Bring up 3 resistors for CNR4 Thermistor measurement
To Do as of 6/8/2013
- Wiring Diagrams
- XX Sketch up site
- holes in box for instrumentation maybe?
- cut crossarms to length (in Barrow)
- Change SDI-12 IDs for SR50As (in Barrow)
- Copy B program additions to A & C
Remaining things to grab
- XXX Nu Rail oddball connectors from cabinet
- XXX BP tubing for grid site
- XXX Cord Grips for grid site
- XXX silicone for grid site
To Purchase
- XXX More Flexible Conduit
- XXX Vent Tube
- XXX Cable Management supplies
- 5/16" Washers
- 13/16" / 3/4" drill bit
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
- XX 1 Novalynx Wind Screen
- XX 1 TE525m & Cable
- Precip Stand (3 sets)
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
- XX 1.5" Nurail offset
- XX 1" Aluminum cross arm for upper AT/RH & WS
- XX HMP155s, cables, Radiation Shield
- XX 014a WS, cables, nurail / cross arm mounts
- Tripod Related
Things to buy
- XXX Bit o' Food?
- 1.5" Pipe Threader
- XXX Flex Conduit
Stuff to bring
Technical Gear
- XXX Keypads
- XXX fish tape
- Tool Bags
- Computer & (packed) SC32B
- Climbing harness
- XXX Serial Cables & spares
- XXX Sawzall
- XXX drill
- XXX Pipe Wrench
- 1.5" Pipe Threader
Food to bring out
- Optional
Rough on-site todo (for each site)
- Measure from top of tripod base to cross arm... note in fieldbook
- Remove box & solar panel from tripod mast
- Remove existing crossarm off tripod
- unscrew center pole
- put 1.5" offset nurail fitting on new center pole
- add top of tower cross arm with anemometer & HMP155
- Armor and secure these two cables
- screw on the new center pole
- put the existing cross arm, instrument box, and solar panel back on the tower.
- Mount all new sensors
- On lowest crossarm, 1-1.5m above ground surface
- Net Radiometer
- Cross Arm bracket
- Wind Speed
- HMP155 on radiometer crossarm
- Armor all the cabling lower cabling
- Armor and install the precip bucket.
- Install the precip wind screen
- On lowest crossarm, 1-1.5m above ground surface
- send new program to data logger
- Bring cabling into the box and wire into the appropriate data logger / multiplexer.
Idealized Rough Itinerary (with dates to float depending on how long things take)
I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.
6/11
- Fly to Barrow
- Sort Shipped Gear
- Track down a sled
- Organize stuff locally in Barrow
- Quick trip to the sites if there is time
- Look at D site box for parts (and prepare for shipment back to Fairbanks)
6/12
- Haul stuff out for A site
- Add components to A site
6/13
- Haul stuff out for B site
- Finish A site
- Start B site
6/14
- Haul stuff out for C site
- Finish B site
- Start C site?
6/15
- Finish C site
6/16
- Ship stuff back to Fairbanks
- Depart for Fairbanks