Difference between revisions of "NGEE Barrow 2013 Site Install Trip 2"
		
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
		
		
		
		
		
	
| (3 intermediate revisions by the same user not shown) | |||
| Line 6: | Line 6: | ||
** Wind Screen 3x  | ** Wind Screen 3x  | ||
** HMP155s 6x  | ** HMP155s 6x  | ||
| − | ** MetOne   | + | ** MetOne 6x  | 
** Barometric Pressure  | ** Barometric Pressure  | ||
** Radiation Shields  | ** Radiation Shields  | ||
| − | ** Cross Arms    | + | ** Cross Arms & Mounts  | 
*** 1.5" Sched 40 Aluminum = Net Radiometer 3x  | *** 1.5" Sched 40 Aluminum = Net Radiometer 3x  | ||
*** 1" Sched 40 Aluminum = Upper WS & AT/RH 3x  | *** 1" Sched 40 Aluminum = Upper WS & AT/RH 3x  | ||
| Line 15: | Line 15: | ||
*** 1.5" Sched 40 Galvanized Pipe  | *** 1.5" Sched 40 Galvanized Pipe  | ||
** Net Radiometer  | ** Net Radiometer  | ||
| + | *** Fan/Heater is in Barrow  | ||
** NuRail Fittings for crossarms  | ** NuRail Fittings for crossarms  | ||
===To Add to each site===  | ===To Add to each site===  | ||
* 2 HMP155s w/ Radiation Shields  | * 2 HMP155s w/ Radiation Shields  | ||
| − | * 2 Met One WS  | + | * 1 pcs 107 radiation shield (bringing it, will mull when looking at as-built.  | 
| + | * 2 Met One 014a WS  | ||
| + | * 3pcs Cross Arm Mounts for each  | ||
| + | ** 3.5m cross arm  | ||
| + | ** 3.5m WS  | ||
| + | ** 1m WS  | ||
* 1 Tipping Bucket w/ Windscreen  | * 1 Tipping Bucket w/ Windscreen  | ||
| + | ** Some alter-shield NuRail fittings are on site.  Check the battery box I think?... also may have been repurposed for snow sensors, my notes are unclear.  Also check the D site box in storage.  | ||
* 1 CNR4 Net Radiometer with Heater/Fan Control  | * 1 CNR4 Net Radiometer with Heater/Fan Control  | ||
| − | * 1 AM16/  | + | * 1 AM16/32B inside the box  | 
| + | * Cable Management inside the box (new cable list:)  | ||
| + | ** 2 pcs 014a  | ||
| + | ** 2 pcs hmp155  | ||
| + | ** 3 pcs cnr4  | ||
| + | * might go looking for a short steel cable of some sort to run down the pipe.  | ||
| + | * Anything else?  | ||
===Additionally, to add to Grid Site===  | ===Additionally, to add to Grid Site===  | ||
| − | * CS106 Barometric Pressure  | + | * Maybe?  Still on the fence about this due to ground location of the box.  CS106 Barometric Pressure.  Could also add to A yet.  | 
** Need to dig out a vent tube  | ** Need to dig out a vent tube  | ||
** Bring up parts to put a new hole in this enclosure  | ** Bring up parts to put a new hole in this enclosure  | ||
| + | * Finish MD485 Networking.  | ||
| + | * Silicone up Grid Box new hole (md485 cable)  | ||
| + | |||
===Rewiring at each site===  | ===Rewiring at each site===  | ||
* Move AM16/32B #1 & #2 RES to CR1000 C1  | * Move AM16/32B #1 & #2 RES to CR1000 C1  | ||
| Line 35: | Line 51: | ||
*** #2 = ID8  | *** #2 = ID8  | ||
*** #3 = ID9  | *** #3 = ID9  | ||
| − | * Also Measure Thermal Conductivity Heater Values  | + | * XX Also Measure Thermal Conductivity Heater Values  | 
| − | * Bring up 3 resistors for CNR4 Thermistor measurement  | + | * XX Bring up 3 resistors for CNR4 Thermistor measurement  | 
===To Do as of 6/8/2013===  | ===To Do as of 6/8/2013===  | ||
* Wiring Diagrams  | * Wiring Diagrams  | ||
| − | * Sketch up site  | + | * XX Sketch up site  | 
* holes in box for instrumentation maybe?  | * holes in box for instrumentation maybe?  | ||
* cut crossarms to length (in Barrow)  | * cut crossarms to length (in Barrow)  | ||
| Line 50: | Line 66: | ||
=== Remaining things to grab===  | === Remaining things to grab===  | ||
* XXX Nu Rail oddball connectors from cabinet  | * XXX Nu Rail oddball connectors from cabinet  | ||
| − | * BP tubing for grid site  | + | * XXX BP tubing for grid site  | 
| − | *   | + | * XXX Cord Grips for grid site  | 
| − | * silicone for grid site  | + | * XXX silicone for grid site  | 
===To Purchase===  | ===To Purchase===  | ||
| − | * More Flexible Conduit  | + | * XXX More Flexible Conduit  | 
| − | * Vent Tube  | + | * XXX Vent Tube  | 
| + | * XXX Cable Management supplies  | ||
| + | * '''5/16" Washers'''  | ||
| + | * '''13/16" /  3/4" drill bit'''  | ||
===Pre-trip to do===  | ===Pre-trip to do===  | ||
| Line 72: | Line 91: | ||
*** XX HMP155s, cables, Radiation Shield  | *** XX HMP155s, cables, Radiation Shield  | ||
*** XX 014a WS, cables, nurail / cross arm mounts  | *** XX 014a WS, cables, nurail / cross arm mounts  | ||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
| − | |||
===Things to buy===  | ===Things to buy===  | ||
| − | * Bit o' Food?  | + | * XXX Bit o' Food?  | 
* 1.5" Pipe Threader  | * 1.5" Pipe Threader  | ||
| − | * Flex Conduit  | + | * XXX Flex Conduit  | 
===Stuff to bring===  | ===Stuff to bring===  | ||
==== Technical Gear ====  | ==== Technical Gear ====  | ||
| − | * Keypads  | + | * XXX Keypads  | 
| − | *   | + | * XXX fish tape  | 
* Tool Bags    | * Tool Bags    | ||
* Computer & (packed) SC32B    | * Computer & (packed) SC32B    | ||
* Climbing harness  | * Climbing harness  | ||
| − | * Serial Cables & spares  | + | * XXX Serial Cables & spares  | 
| − | *   | + | * XXX Sawzall  | 
| − | *   | + | * XXX drill  | 
| − | * Pipe Wrench  | + | * XXX Pipe Wrench  | 
* 1.5" Pipe Threader  | * 1.5" Pipe Threader  | ||
| Line 123: | Line 136: | ||
## Install the precip wind screen  | ## Install the precip wind screen  | ||
# send new program to data logger  | # send new program to data logger  | ||
| + | ## Bring cabling into the box and wire into the appropriate data logger / multiplexer.  | ||
| + | |||
====Idealized Rough Itinerary (with dates to float depending on how long things take)====  | ====Idealized Rough Itinerary (with dates to float depending on how long things take)====  | ||
Latest revision as of 16:10, 10 June 2013
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
 - Wind Screen 3x
 - HMP155s 6x
 - MetOne 6x
 - Barometric Pressure
 - Radiation Shields
 - Cross Arms & Mounts
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
 - 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
 
 - Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
 
 - Net Radiometer
- Fan/Heater is in Barrow
 
 - NuRail Fittings for crossarms
 
 
To Add to each site
- 2 HMP155s w/ Radiation Shields
 - 1 pcs 107 radiation shield (bringing it, will mull when looking at as-built.
 - 2 Met One 014a WS
 - 3pcs Cross Arm Mounts for each
- 3.5m cross arm
 - 3.5m WS
 - 1m WS
 
 - 1 Tipping Bucket w/ Windscreen
- Some alter-shield NuRail fittings are on site. Check the battery box I think?... also may have been repurposed for snow sensors, my notes are unclear. Also check the D site box in storage.
 
 - 1 CNR4 Net Radiometer with Heater/Fan Control
 - 1 AM16/32B inside the box
 - Cable Management inside the box (new cable list:)
- 2 pcs 014a
 - 2 pcs hmp155
 - 3 pcs cnr4
 
 - might go looking for a short steel cable of some sort to run down the pipe.
 - Anything else?
 
Additionally, to add to Grid Site
- Maybe?  Still on the fence about this due to ground location of the box.  CS106 Barometric Pressure.  Could also add to A yet.
- Need to dig out a vent tube
 - Bring up parts to put a new hole in this enclosure
 
 - Finish MD485 Networking.
 - Silicone up Grid Box new hole (md485 cable)
 
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
 - Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
 - #2 = ID8
 - #3 = ID9
 
 
 - Reprogram the IDs for the SR50As
 - XX Also Measure Thermal Conductivity Heater Values
 - XX Bring up 3 resistors for CNR4 Thermistor measurement
 
To Do as of 6/8/2013
- Wiring Diagrams
 - XX Sketch up site
 - holes in box for instrumentation maybe?
 - cut crossarms to length (in Barrow)
 - Change SDI-12 IDs for SR50As (in Barrow)
 - Copy B program additions to A & C
 
Remaining things to grab
- XXX Nu Rail oddball connectors from cabinet
 - XXX BP tubing for grid site
 - XXX Cord Grips for grid site
 - XXX silicone for grid site
 
To Purchase
- XXX More Flexible Conduit
 - XXX Vent Tube
 - XXX Cable Management supplies
 - 5/16" Washers
 - 13/16" / 3/4" drill bit
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand  (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
 - XX 1 Novalynx Wind Screen
 - XX 1 TE525m & Cable
 
 
 - Precip Stand  (3 sets)
 
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
 - XX 1.5" Nurail offset
 - XX 1" Aluminum cross arm for upper AT/RH & WS
 - XX HMP155s, cables, Radiation Shield
 - XX 014a WS, cables, nurail / cross arm mounts
 
 
- Tripod Related
 
Things to buy
- XXX Bit o' Food?
 - 1.5" Pipe Threader
 - XXX Flex Conduit
 
Stuff to bring
Technical Gear
- XXX Keypads
 - XXX fish tape
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - XXX Serial Cables & spares
 - XXX Sawzall
 - XXX drill
 - XXX Pipe Wrench
 - 1.5" Pipe Threader
 
Food to bring out
- Optional
 
Rough on-site todo (for each site)
- Measure from top of tripod base to cross arm... note in fieldbook
 - Remove box & solar panel from tripod mast
 - Remove existing crossarm off tripod
 - unscrew center pole
 - put 1.5" offset nurail fitting on new center pole
 - add top of tower cross arm with anemometer & HMP155
- Armor and secure these two cables
 
 - screw on the new center pole
 - put the existing cross arm, instrument box, and solar panel back on the tower.
 - Mount all new sensors
- On lowest crossarm, 1-1.5m above ground surface
- Net Radiometer
 - Cross Arm bracket
- Wind Speed
 
 - HMP155 on radiometer crossarm
 
 - Armor all the cabling lower cabling
 - Armor and install the precip bucket.
 - Install the precip wind screen
 
 - On lowest crossarm, 1-1.5m above ground surface
 - send new program to data logger
- Bring cabling into the box and wire into the appropriate data logger / multiplexer.
 
 
Idealized Rough Itinerary (with dates to float depending on how long things take)
I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.
6/11
- Fly to Barrow
 - Sort Shipped Gear
 - Track down a sled
 - Organize stuff locally in Barrow
 - Quick trip to the sites if there is time
 - Look at D site box for parts (and prepare for shipment back to Fairbanks)
 
6/12
- Haul stuff out for A site
 - Add components to A site
 
6/13
- Haul stuff out for B site
 - Finish A site
 - Start B site
 
6/14
- Haul stuff out for C site
 - Finish B site
 - Start C site?
 
6/15
- Finish C site
 
6/16
- Ship stuff back to Fairbanks
 - Depart for Fairbanks