Difference between revisions of "2021 NGEE Nome August Trip"
Jump to navigation
Jump to search
Line 1: | Line 1: | ||
− | + | NGEE Project Disturbance / Kougarok focus. Helping Go mostly. | |
* Plan to visit all three Kougarok met stations... | * Plan to visit all three Kougarok met stations... | ||
+ | * Measure ground control at NGEE Koguarok mile 64 site | ||
* Thaw depth and subsidence survey | * Thaw depth and subsidence survey | ||
− | * Measure creek flow | + | * Measure creek flow at Teller mile 27 site |
+ | (Most of this trip itinerary is beign driven by Go) |
Revision as of 08:53, 23 July 2021
NGEE Project Disturbance / Kougarok focus. Helping Go mostly.
- Plan to visit all three Kougarok met stations...
- Measure ground control at NGEE Koguarok mile 64 site
- Thaw depth and subsidence survey
- Measure creek flow at Teller mile 27 site
(Most of this trip itinerary is beign driven by Go)