Difference between revisions of "NGEE Barrow 2013 Site Install Trip"
		
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
		
		
		
		
		
	
| Line 1: | Line 1: | ||
| − | |||
===Shipping===  | ===Shipping===  | ||
* New Instrumentation once it arrives:  | * New Instrumentation once it arrives:  | ||
| Line 5: | Line 4: | ||
** Wind Screen 3x  | ** Wind Screen 3x  | ||
** HMP155s 6x  | ** HMP155s 6x  | ||
| − | ** MetOne   | + | ** MetOne 5x  | 
** Barometric Pressure  | ** Barometric Pressure  | ||
** Leg Mount Instrument Boxes 3x  | ** Leg Mount Instrument Boxes 3x  | ||
| Line 16: | Line 15: | ||
** Tripod Mast  | ** Tripod Mast  | ||
*** 1.5" Sched 40 Galvanized Pipe  | *** 1.5" Sched 40 Galvanized Pipe  | ||
| + | |||
| + | ===To Add to each site===  | ||
| + | * 2 HMP155s w/ Radiation Shields  | ||
| + | * 2 Met One WS (only one for Site A)  | ||
| + | * 1 Tipping Bucket w/ Windscreen  | ||
| + | * 1 CNR4 Net Radiometer with Heater/Fan Control  | ||
| + | * 1 Leg Mounted Enclosure  | ||
| + | * 1 SDM Based IO Expander  | ||
| + | * 1 AM16/32  | ||
| + | ===Additionally, to add to Site A===  | ||
| + | * CS106 Barometric Pressure  | ||
| + | * RM Young Anemometer  | ||
===To Do as of 4/10/2013===  | ===To Do as of 4/10/2013===  | ||
Revision as of 20:32, 11 April 2013
Contents
Shipping
- New Instrumentation once it arrives:
- Precip Buckets 3x
 - Wind Screen 3x
 - HMP155s 6x
 - MetOne 5x
 - Barometric Pressure
 - Leg Mount Instrument Boxes 3x
- Install AM16/32B if time
 - Install SDM Switch if time
 
 - Radiation Shields
 - Cross Arms
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
 - 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
 
 - Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
 
 
 
To Add to each site
- 2 HMP155s w/ Radiation Shields
 - 2 Met One WS (only one for Site A)
 - 1 Tipping Bucket w/ Windscreen
 - 1 CNR4 Net Radiometer with Heater/Fan Control
 - 1 Leg Mounted Enclosure
 - 1 SDM Based IO Expander
 - 1 AM16/32
 
Additionally, to add to Site A
- CS106 Barometric Pressure
 - RM Young Anemometer
 
To Do as of 4/10/2013
- Modify Programs
 - Wiring Diagrams
 - PRs for freight
 - Sketch up site
 - Wire up boxes as much as possible (is anything possible? Maybe just mount the peripherals)
 - cut crossarms to length
 
Remaining things to grab
- ?
 
To Purchase
- ?
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand  (3 sets)
- 4 NuRail 3/4 offset cross pieces
 - 1 Novalynx Wind Screen
 - 1 TE525m & Cable
 
 
 - Precip Stand  (3 sets)
 
- Tripod Related
 - 
 
- Tripod Related
 
Things to buy
- Bit o' Food?
 - ?
 
Stuff to bring
things not on a PR yet
Technical Gear
- Shotgun
 - Keypads
 - fish tape
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Climbing Gear Proper
 - Serial Cables & spares
 - Sawzall
 - drill
 
Food to bring out
- Optional
 
Probable Luggage
- Shotgun [Bob #1]
 - Bob Personal backpack [Bob #2]
 - Work Actionpacker #1 [Bob #3]
 
Rough on-site todo
- Remove box & solar panel
 - Measure from top of tripod base to cross arm... note in fieldbook
 - Remove crossarm off tripod
 - unscrew center pole
 - put 1.5" offset nurail fitting on new center pole
 - attach new center pole
 - put cross arm, instrument box, and solar panel back on the tower.
 - Install new instrument box on lower leg.
 - Mount all new sensors
- Net Radiometer @ 1-1.5m
 - WS on radiometer crossarm
 - HMP155 on radiometer crossarm
 - Second HMP155 & WS high up on tower, maybe as high as they'll reach.
 - Armor all the cabling
 - Armor and install the precip bucket.
 - Install the precip wind screen
 
 - send new program to data logger