===To Purchase in town etc===
 
===To Purchase in town etc===
* after leg supports are in place will need to pick up lag bolts for anchor base mounts
+
* after leg supports are in place will need to pick up lag bolts for anchor base mounts / ice freezes
 +
* check out the metal plates in the cement section at home depot.  Grab four plates to place below the legs.
 +
 
 +
===Extra to bring out Monday===
 +
* cordless battery charger
 +
* more exterior wood screws
 +
* proper bit for the wood screws
  
 
===Tools needed Thursday===
 
===Tools needed Thursday===
Line 14: Line 20:
 
* Wood Screws & washers to secure unistrut to trailer
 
* Wood Screws & washers to secure unistrut to trailer
 
* tie downs to secure pipe to trailer
 
* tie downs to secure pipe to trailer
 +
 +
===Plan for 1st week of October===
 +
* put metal plates under the the two south side supports
 +
* use four of the scaffold clamps to secure each south side leg in two places to the extra scaffolding added by Ikawa.
 +
* once those are in place then add the remaining clamps to the south side supports.
 +
* with the south side complete, lock in place the weak leg support.
 +
* with the it in place and fully clamped, remove the original helper.
 +
* put in a secondary 10' support on the NW leg
 +
* move the fourth pipe to the NE corner
 +
* clamp up the NE corner leg support.
 +
* with the legs fully clamped, start on the guy wires. 
 +
  
 
====Bolting hardware====
 
====Bolting hardware====
Line 19: Line 37:
 
* Type 316 Stainless Steel Nylon-Insert Locknut, 3/8"-16 Thread Size
 
* Type 316 Stainless Steel Nylon-Insert Locknut, 3/8"-16 Thread Size
 
* Zinc Yellow-Chromate Plated Steel Flat Washer, Grade 9, 3/8" Screw Size
 
* Zinc Yellow-Chromate Plated Steel Flat Washer, Grade 9, 3/8" Screw Size
 
===Thursday Plan===
 
* Pick up vehicle at FS
 
** load vehicle with all my other tools & equipment
 
** toss in the key card for PFRR
 
* drive to north pole & White Spruce (before NP proper)
 
* Return to campus & load up trailer
 
** screw uni-strut to trailer
 
** secure rest of pipe to trailer
 
* drive to PFRR & unload pipe
 
* Move pipe & 16 of the 96 clamps to the shed area, probably in cart.
 
* move the four earth anchors from the vehicle to the shed area.
 
* bring the tools to the shed
 
* Cut the 8x8 timber to size using the sawzall
 
* place the timber on the ground supports
 
* put the bottom piece on the pipe.
 
* secure the first pipe at the bottom with the clamps & bolts/nuts/washers (2 per clamp)
 
* secure the first pipe at the top with the clamps & bolts/nuts/washers (2 per clamp)
 
* repeat for the other three pipes
 
 
===Friday Plan===
 
* secure any remaining pipes top & bottom
 
* Screw in the four earth anchors
 
* start securing in the remaining 10 clamps per leg.
 
* install on the shed the hooks for the top pulley deal
 
 
===Plan for 1st week of October===
 
* continue securing the clamps
 
 
  
 
===Extra Notes===
 
===Extra Notes===

Revision as of 14:13, 30 September 2016

To Purchase in town etc

  • after leg supports are in place will need to pick up lag bolts for anchor base mounts / ice freezes
  • check out the metal plates in the cement section at home depot. Grab four plates to place below the legs.

Extra to bring out Monday

  • cordless battery charger
  • more exterior wood screws
  • proper bit for the wood screws

Tools needed Thursday

  • Lunch
  • wired Sawzall with long blade for cutting 8x8" lumber
  • extra long sawzall blade
  • tool belt, small
  • 9/16" Wrench & nut driver / socket
  • gorilla cart
  • cordless drill for hangers
  • 2 pcs uni-strut
  • 8 pcs uni-strut clamps
  • Wood Screws & washers to secure unistrut to trailer
  • tie downs to secure pipe to trailer

Plan for 1st week of October

  • put metal plates under the the two south side supports
  • use four of the scaffold clamps to secure each south side leg in two places to the extra scaffolding added by Ikawa.
  • once those are in place then add the remaining clamps to the south side supports.
  • with the south side complete, lock in place the weak leg support.
  • with the it in place and fully clamped, remove the original helper.
  • put in a secondary 10' support on the NW leg
  • move the fourth pipe to the NE corner
  • clamp up the NE corner leg support.
  • with the legs fully clamped, start on the guy wires.


Bolting hardware

  • Medium-Strength Grade 5 Zinc-Plated Steel Cap Screw, 3/8"-16 Thread, 4" Long
  • Type 316 Stainless Steel Nylon-Insert Locknut, 3/8"-16 Thread Size
  • Zinc Yellow-Chromate Plated Steel Flat Washer, Grade 9, 3/8" Screw Size

Extra Notes

  • the cyberpower below the SS Toughbook may be at capacity. Or who knows. There was a power surge that tripped it, which brought the network down when the deal didn't come back up.
  • something to keep an eye on. It coincided perhaps with an 8/21 visit.
  • it is a recurring brown out but I'm not sure yet if it is hitting everything or just that UPS.
  • probably need an extension to reconnect the HMP power.

Super Site Activity Log