(Created page with "* Site C HMP155 * Check level of radiometers * Replace SR50A transducers * Check level of tipping buckets *") |
|||
Line 1: | Line 1: | ||
− | * Site C HMP155 | + | ===To Do=== |
+ | |||
+ | |||
+ | * Intensive Site A HMP155 failed (3.5m) | ||
+ | * Intensive Site B HMP155 failed (1.4m) | ||
+ | * Intensive Site C HMP155 failed | ||
+ | * Have 2-3 additional HMP155 membrane tips | ||
+ | * need to replace the network cable running from the computer to the network switch. It cuts out with minimal bumping... | ||
+ | * Site A SR50A transducers have failed | ||
+ | * Check level of tipping buckets | ||
* Check level of radiometers | * Check level of radiometers | ||
− | * | + | ** replace radiometer desiccant |
− | * | + | ** polish radiometer domes |
− | * | + | * some subsurface items are beginning to fail. |
+ | * label the computer | ||
+ | * bring up the nuc plate and wood screws and other screw packet to mount nuc to wall | ||
+ | * troubleshoot the network connection in control shed. | ||
+ | * take new pictures of inside control shed | ||
+ | |||
+ | ===To Bring=== | ||
+ | * Tools | ||
+ | ** CSI Phillips for opening CNR4 radiometers and SR50A | ||
+ | ** Tap & Die in case any more radiometer screws strip | ||
+ | ** torpedo level for tipping bucket level | ||
+ | ** 5/16" screw driver for tipping bucket level | ||
+ | ** electrical tape for HMP155 replacement | ||
+ | ** Antenna & coax for C site to get antenna outside of the box. (two different antennas will decide on which up in Utqiagvik) | ||
+ | ** Drill & battery for potential tap & die stuff | ||
+ | |||
+ | |||
+ | ===On Site=== | ||
+ | * Should be a ladder at the NGEE Flux tower for use replacing 3.5m instruments |
Revision as of 12:19, 29 September 2018
To Do
- Intensive Site A HMP155 failed (3.5m)
- Intensive Site B HMP155 failed (1.4m)
- Intensive Site C HMP155 failed
- Have 2-3 additional HMP155 membrane tips
- need to replace the network cable running from the computer to the network switch. It cuts out with minimal bumping...
- Site A SR50A transducers have failed
- Check level of tipping buckets
- Check level of radiometers
- replace radiometer desiccant
- polish radiometer domes
- some subsurface items are beginning to fail.
- label the computer
- bring up the nuc plate and wood screws and other screw packet to mount nuc to wall
- troubleshoot the network connection in control shed.
- take new pictures of inside control shed
To Bring
- Tools
- CSI Phillips for opening CNR4 radiometers and SR50A
- Tap & Die in case any more radiometer screws strip
- torpedo level for tipping bucket level
- 5/16" screw driver for tipping bucket level
- electrical tape for HMP155 replacement
- Antenna & coax for C site to get antenna outside of the box. (two different antennas will decide on which up in Utqiagvik)
- Drill & battery for potential tap & die stuff
On Site
- Should be a ladder at the NGEE Flux tower for use replacing 3.5m instruments