===Tasks=== | ===Tasks=== | ||
+ | ====Bob from Camp==== | ||
+ | * Load helo up with gaging equipment for the culvert site. | ||
====Itkillik Station==== | ====Itkillik Station==== | ||
− | * | + | * Measure bumper & bottom of R8 to GPS Master 2 again |
− | * | + | * Retrieve GPS Unit for Bob |
* Snow Survey | * Snow Survey | ||
** Everything is on site | ** Everything is on site | ||
− | * Start Surveying | + | * Start Surveying |
* Paint top of culvert | * Paint top of culvert | ||
* Standard aerial pictures of gaging cross-section | * Standard aerial pictures of gaging cross-section | ||
* Identify Dye Locations (Start & Finish) | * Identify Dye Locations (Start & Finish) | ||
− | * Start @ Station | + | ** Start @ Station |
− | * Look for good downriver Locations | + | ** Look for good downriver Locations |
====Itkillik River Crossing==== | ====Itkillik River Crossing==== | ||
* Pictures @ Bridge crossing | * Pictures @ Bridge crossing | ||
** Digital Camera | ** Digital Camera | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
====Peak Flow Gaging Site==== | ====Peak Flow Gaging Site==== | ||
Line 38: | Line 33: | ||
* Spare Hobo (@Toolik) | * Spare Hobo (@Toolik) | ||
** Program in camp on 5/18 | ** Program in camp on 5/18 | ||
+ | * Make a GPS Master 3 near the third hobo down river. | ||
* hobo environmental protection (@snowmachine trailer) | * hobo environmental protection (@snowmachine trailer) | ||
* steel cable (in helicopter) | * steel cable (in helicopter) | ||
Line 59: | Line 55: | ||
* Shovels (in helicopter) | * Shovels (in helicopter) | ||
− | === | + | ===Bob in Toolik=== |
* Update firmware on streampro | * Update firmware on streampro | ||
* Follow up on Ken's email about other station work | * Follow up on Ken's email about other station work | ||
Line 69: | Line 65: | ||
===Things to do on another day at the Itkillik=== | ===Things to do on another day at the Itkillik=== | ||
− |
Revision as of 07:28, 19 May 2011
Contents
Coordinates
Itkillik Station -- Lat: 68 51.991, Lon: -150 2.400, Elev: 458 meters (1504 feet)
Northern Extent of Open Water -- Lat: N68 40,331, Lon: -149 50.279
PlantCam -- Lat: N68 54.757, Lon: -150 05.697
Hobo #2 -- Lat: N68 52 13.1", Lon: - 150 02 59.2"
Hobo #3 -- Lat: N68 52 44.72", Lon: -150 03 57.63"
Probable Peak Flow Gaging Location -- Lat: N68
Tasks
Bob from Camp
- Load helo up with gaging equipment for the culvert site.
Itkillik Station
- Measure bumper & bottom of R8 to GPS Master 2 again
- Retrieve GPS Unit for Bob
- Snow Survey
- Everything is on site
- Start Surveying
- Paint top of culvert
- Standard aerial pictures of gaging cross-section
- Identify Dye Locations (Start & Finish)
- Start @ Station
- Look for good downriver Locations
Itkillik River Crossing
- Pictures @ Bridge crossing
- Digital Camera
Peak Flow Gaging Site
- Settle on a location (Get a visual of it)
Hobo #3 Location
- Spare Hobo (@Toolik)
- Program in camp on 5/18
- Make a GPS Master 3 near the third hobo down river.
- hobo environmental protection (@snowmachine trailer)
- steel cable (in helicopter)
- cable clamps (with Bill)
- weight (in helicopter?)
- sledge hammer (in helicopter)
- screed stakes (in helicopter)
- 1 for hobo in river
- 1 for hobo anchor on the bank
- 1 for GPS Master 3
- Tools --
- 5/16" Nut Driver for hose clamps
- 1/4" wrench or leatherman for steel cable clamps
- shovel or two
- ice pick
- breaker bar
Tools
- Bob's toolbags (in helicopter)
- Shovels (in helicopter)
Bob in Toolik
- Update firmware on streampro
- Follow up on Ken's email about other station work
- Line out coordinates and a game plan for these sites
- Test out GPS scripts with StreamPro
- Start Daily Backups
- Move the rest of the gear to the station