Line 7: | Line 7: | ||
* Finish Anchors | * Finish Anchors | ||
* Wire AT/RH | * Wire AT/RH | ||
− | * send program to met logger | + | * send new program to met logger |
− | + | Computer work | |
* change scp in camera scripts to rsync | * change scp in camera scripts to rsync | ||
** ''rsync -avz -e "ssh -p 22 -i ~/.ssh/rsync-key" /local_image_dir/ pfss@main_server.iarc.uaf.edu:/remote_destination/'' | ** ''rsync -avz -e "ssh -p 22 -i ~/.ssh/rsync-key" /local_image_dir/ pfss@main_server.iarc.uaf.edu:/remote_destination/'' | ||
Line 22: | Line 22: | ||
* net radiometers | * net radiometers | ||
* anemometers | * anemometers | ||
− | * | + | |
+ | CPCRW At some point type Shopping List: | ||
+ | * For better anchoring stations to prevent tippage: | ||
+ | ** Screw in Anchors (like dog run style) | ||
+ | ** 1 package of tiedowns | ||
+ | * nu-rail fittings for WS? | ||
+ | * ubolt deals for net radiometers? | ||
+ | |||
+ | ''The SFL station was completely knocked over. There was water in the box but everything was still running. I did my best to set everything back up again; it's heavy stuff! Nothing was chewed up though, it just looked like a conga line came through.'' | ||
+ | |||
+ | ''I thought I had fixed the wire between the solar panel and the box but apparently my fix didn't work. The battery isn't charging and starting to get dangerously low. I think the high leaf area is shading the solar panels because the SFH site is having issues with the battery charging up.'' | ||
+ | |||
+ | ''The temp/RH probes at SFL and NFL aren't working. I'm not sure if the ppt bucket at SFL is working; the wire got chewed at one point. The upper sites seem to be surviving.'' |
Revision as of 13:20, 7 July 2011
Combo with CPCRW trip maybe. In Fairbanks
- Add 2 AT/RH to measurements and outputs.
- Drill holes for ubolts
Fieldwork
- Finish Anchors
- Wire AT/RH
- send new program to met logger
Computer work
- change scp in camera scripts to rsync
- rsync -avz -e "ssh -p 22 -i ~/.ssh/rsync-key" /local_image_dir/ pfss@main_server.iarc.uaf.edu:/remote_destination/
- set computer up to restart nightly so this wireless disconnection stops being a bother.
- 50 1 * * * /sbin/shutdown -r now
- log temperatures and wireless signal strength, refresh brain on what I have set up up there
CPCRW Trip:
- Download data from all four sites
- bring out solder and soldering iron to patch up chopped up wires
- electrical tape
- net radiometers
- anemometers
CPCRW At some point type Shopping List:
- For better anchoring stations to prevent tippage:
- Screw in Anchors (like dog run style)
- 1 package of tiedowns
- nu-rail fittings for WS?
- ubolt deals for net radiometers?
The SFL station was completely knocked over. There was water in the box but everything was still running. I did my best to set everything back up again; it's heavy stuff! Nothing was chewed up though, it just looked like a conga line came through.
I thought I had fixed the wire between the solar panel and the box but apparently my fix didn't work. The battery isn't charging and starting to get dangerously low. I think the high leaf area is shading the solar panels because the SFH site is having issues with the battery charging up.
The temp/RH probes at SFL and NFL aren't working. I'm not sure if the ppt bucket at SFL is working; the wire got chewed at one point. The upper sites seem to be surviving.