Difference between revisions of "NGEE September 3 2012 Trip"
		
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
		
		
		
		
		
	
| Line 7: | Line 7: | ||
* [[NGEE-Barrow Calibration and Serial Numbers]]  | * [[NGEE-Barrow Calibration and Serial Numbers]]  | ||
* Timezone - UTC  | * Timezone - UTC  | ||
| − | * PakBus IDs - A = 400; B = 401; C = 402; D = 403  | + |  * PakBus IDs - A = 400; B = 401; C = 402; D = 403  | 
===Supplies / Equipment the GIPL is providing to the project that will need to be replaced===  | ===Supplies / Equipment the GIPL is providing to the project that will need to be replaced===  | ||
| Line 18: | Line 18: | ||
* 8 AM16/32 Multiplexers  | * 8 AM16/32 Multiplexers  | ||
* 4 CR1000s  | * 4 CR1000s  | ||
| − | * Instrument box  | + | * 4 Instrument box  | 
| − | * charge controller  | + | * 4 charge controller (SS10)  | 
| + | * 7 SW12V units  | ||
| + | * 12 HFP01s  | ||
| + | * 12 HydraProbe IIs  | ||
=== Supplies / Equipment IARC is providing to the project that will need to be replaced===  | === Supplies / Equipment IARC is providing to the project that will need to be replaced===  | ||
| Line 42: | Line 45: | ||
* Cut Pipe  | * Cut Pipe  | ||
* Ship stuff: thinking two loads  | * Ship stuff: thinking two loads  | ||
| − | ** shipment 1 ship Wednesday and that will be stuff we'll need on arrival  | + | ** shipment 1 ship Wednesday   and that will be stuff we'll need on arrival  | 
** shipment 2 ship Friday and that will be things still being prepped early next week.  | ** shipment 2 ship Friday and that will be things still being prepped early next week.  | ||
* Organize per site items  | * Organize per site items  | ||
| Line 100: | Line 103: | ||
* 2400 ft of 3/4" flex conduit  | * 2400 ft of 3/4" flex conduit  | ||
* 100 ft of 3/8" flex conduit  | * 100 ft of 3/8" flex conduit  | ||
| − | * brown tarps  | + | * brown tarps (Freds)  | 
| − | * solar panel mounts  | + | * solar panel mounts (Lowes)  | 
* wiring stuff (to control all the excess wires) Action Packers?  | * wiring stuff (to control all the excess wires) Action Packers?  | ||
* conduit, lots!  | * conduit, lots!  | ||
| Line 107: | Line 110: | ||
* fittings for an additional opening in bottom of enclosures  | * fittings for an additional opening in bottom of enclosures  | ||
* cable ties  | * cable ties  | ||
| + | * SDI cable extensions  | ||
===Stuff to bring out===  | ===Stuff to bring out===  | ||
==== Extras from Bill ====  | ==== Extras from Bill ====  | ||
| − | *   | + | * Heat shrink  | 
| + | * Heat Gun  | ||
==== Other ====  | ==== Other ====  | ||
| − | *    | + | * Hole Saw for additional box holes (currently just a single hole) ... purchased and packed.  | 
| + | |||
==== things not on a PR yet====  | ==== things not on a PR yet====  | ||
Revision as of 19:13, 28 August 2012
Contents
Notes
- NGEE Barrow Intensive Sites Initial Wiring
 - First Program (not including thermal offsets which will be added onsite):
 
Metadata type stuff
- NGEE-Barrow Calibration and Serial Numbers
 - Timezone - UTC
 
* PakBus IDs - A = 400; B = 401; C = 402; D = 403
Supplies / Equipment the GIPL is providing to the project that will need to be replaced
- 4 Tripods
 - 4 CrossArms
 - 4 Radiation Shields
 - 4 107 Temperature Probes
 - 24 Thermal Conductivity sensors from East30
 - 8 Current Excitation Modules
 - 8 AM16/32 Multiplexers
 - 4 CR1000s
 - 4 Instrument box
 - 4 charge controller (SS10)
 - 7 SW12V units
 - 12 HFP01s
 - 12 HydraProbe IIs
 
Supplies / Equipment IARC is providing to the project that will need to be replaced
- Radios
- set hopping channels to an alternate: 13
 - Network ID is 2279 (BARW on phone)
 - set up in multipoint mode
 
 
- RF450 S/N 882-5337; 875-2691;875-2750
 - FGR S/N 873-7563 (Master); 873-5346
 - Need 2 more Null Modems 8/27/2012
 
Enroute
- Battery Boxes should arrive 8/30ish
 - batteries I'm not sure of but should arrive near our departure.
 
Program to do yet
- seasonal snow measurements... not going to do anything special I think.
 - test final program... testing.
 
Pre-trip to do
- Cut Pipe
 - Ship stuff: thinking two loads
- shipment 1 ship Wednesday and that will be stuff we'll need on arrival
 - shipment 2 ship Friday and that will be things still being prepped early next week.
 
 - Organize per site items
- Precip Stand
- 3 screed stakes
 - Pipe: 2 pcs 5 ft; 1 pcs 2.5'
 - Hose Clamps (2 sizes)
 - NuRail fittings (currently in Bob's office)
 
 - Tripod Related
- 1 pcs tripod
 - 1 pcs instrument box & contents:
- cable ties
 - AM16/32s
 - 2 pcs current excitation module
 - 1 pcs CR1000
 - 1 pcs radio & power cable
 - 1 pcs radio antenna setup
 - 1 pcs null modem
 
 - Energy system
- 1 pcs solar panel
 - 2 pcs ubolts for solar panel mount
 - 2 pcs aluminum strips for solar panel mount
 - 4 pcs nuts & bolts for solar panel mount
 - Batteries if they arrive
 - Ring connectors for batteries
 - power cable to go between batteries
 - power cable to go battery box to instrument box
 - cable protection between battery box and instrument box
 - power cable to go between solar panel and battery box
 - cable protection to go between solar panel and battery box
 - cold temperature power cable (red & black or an all-weather extension cord)
 - 1 pcs power cable from solar panel
 - 1 pcs cable protection for solar panel cable (sort of left off cable protection estimates I'm thinking)
 - 1 pcs charge controller
 
 - 1 pcs SR50A setup
- 5' x 3/4" Pipe
 - SR50A setup
 - 1 pcs SR50A
 - 1 pcs SR50A mount
 - 1 pcs SR50A cable
 - 1 pcs SR50A cable protection
 
 - Air Temperature Setup
- 1 pcs AT radiation shield
 - 1 pcs 107 Temperature Probe
 - 1 pcs cable protection
 
 - Subsurface Hardware
- 9 HydraProbe IIs
 - 3 HFP01 heat flux plates
 - 5 deep thermistor probes
 - 1 shallow thermistor probes
 - 9 thermistors probes to pair with the hydraprobe iis
 - 6 thermal conductivity probes to put two of the pits
 
 
 
 - Precip Stand
 
Things to buy
- Bit o' Food?
 - buy additional required hardware
 - 2400 ft of 3/4" flex conduit
 - 100 ft of 3/8" flex conduit
 - brown tarps (Freds)
 - solar panel mounts (Lowes)
 - wiring stuff (to control all the excess wires) Action Packers?
 - conduit, lots!
 - large pvc and fittings to go between action packer and CSI enclosure?
 - fittings for an additional opening in bottom of enclosures
 - cable ties
 - SDI cable extensions
 
Stuff to bring out
Extras from Bill
- Heat shrink
 - Heat Gun
 
Other
- Hole Saw for additional box holes (currently just a single hole) ... purchased and packed.
 
things not on a PR yet
- power cables (reds & blacks or extension cords)
 - cable protection for energy system
 - brown tarps from Freddies
 - NRS straps maybe from the Beave for the tarp.
 - Cable Ties
 - Terminal strips
 
Equipment To Ship
- 4 Tripods
 - 4 Battery Boxes
 - 4 Solar Panels
 - Thermistor Strings
 - Additional Thermistors
 - Radiation Shields
 - Instrument boxes with loggers etc. installed
 - charge controllers
 
Technical Gear
- Shotgun
 - Keypad
 - fish tape
 - kayak
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Climbing Gear Proper
 - Serial Cables & spares
 - brown tarps
 - Sawzall
 - drill
 
Food to bring out
- Optional
 
Probable Luggage
- Shotgun [Bob #1]
 - Bob Personal backpack [Bob #2]
 - Work Actionpacker #1 [Bob #3]
 
How it will go down out there
- Bil & Vlad drill the thermistor bore holes
 - Bob focuses on the wiring and station set up with an assist as needed from others
 - Anna if she comes digs and logs soil pits
 - All will share hauling duties from truck to intensive site area