Difference between revisions of "NGEE September 3 2012 Trip"

From IARC 207 Wiki
Jump to navigation Jump to search
Line 7: Line 7:
 
* [[NGEE-Barrow Calibration and Serial Numbers]]
 
* [[NGEE-Barrow Calibration and Serial Numbers]]
 
* Timezone - UTC
 
* Timezone - UTC
* PakBus IDs - A = 400; B = 401; C = 402; D = 403
+
* PakBus IDs - A = 400; B = 401; C = 402; D = 403
  
 
===Supplies / Equipment the GIPL is providing to the project that will need to be replaced===
 
===Supplies / Equipment the GIPL is providing to the project that will need to be replaced===
Line 18: Line 18:
 
* 8 AM16/32 Multiplexers
 
* 8 AM16/32 Multiplexers
 
* 4 CR1000s
 
* 4 CR1000s
* Instrument box
+
* 4 Instrument box
* charge controller
+
* 4 charge controller (SS10)
 +
* 7 SW12V units
 +
* 12 HFP01s
 +
* 12 HydraProbe IIs
  
 
=== Supplies / Equipment IARC is providing to the project that will need to be replaced===
 
=== Supplies / Equipment IARC is providing to the project that will need to be replaced===
Line 42: Line 45:
 
* Cut Pipe
 
* Cut Pipe
 
* Ship stuff: thinking two loads
 
* Ship stuff: thinking two loads
** shipment 1 ship Wednesday and that will be stuff we'll need on arrival
+
** shipment 1 ship Wednesday   and that will be stuff we'll need on arrival
 
** shipment 2 ship Friday and that will be things still being prepped early next week.
 
** shipment 2 ship Friday and that will be things still being prepped early next week.
 
* Organize per site items
 
* Organize per site items
Line 100: Line 103:
 
* 2400 ft of 3/4" flex conduit
 
* 2400 ft of 3/4" flex conduit
 
* 100 ft of 3/8" flex conduit
 
* 100 ft of 3/8" flex conduit
* brown tarps
+
* brown tarps (Freds)
* solar panel mounts
+
* solar panel mounts (Lowes)
 
* wiring stuff (to control all the excess wires) Action Packers?
 
* wiring stuff (to control all the excess wires) Action Packers?
 
* conduit, lots!
 
* conduit, lots!
Line 107: Line 110:
 
* fittings for an additional opening in bottom of enclosures
 
* fittings for an additional opening in bottom of enclosures
 
* cable ties
 
* cable ties
 +
* SDI cable extensions
  
 
===Stuff to bring out===
 
===Stuff to bring out===
 
==== Extras from Bill ====
 
==== Extras from Bill ====
* 4 pcs 107 Probes & Radiation Shields
+
* Heat shrink
 +
* Heat Gun
  
  
 
==== Other ====
 
==== Other ====
*  
+
* Hole Saw for additional box holes (currently just a single hole) ... purchased and packed.
 +
 
  
 
==== things not on a PR yet====
 
==== things not on a PR yet====

Revision as of 19:13, 28 August 2012

Notes

Metadata type stuff

* PakBus IDs - A = 400; B = 401; C = 402; D = 403

Supplies / Equipment the GIPL is providing to the project that will need to be replaced

  • 4 Tripods
  • 4 CrossArms
  • 4 Radiation Shields
  • 4 107 Temperature Probes
  • 24 Thermal Conductivity sensors from East30
  • 8 Current Excitation Modules
  • 8 AM16/32 Multiplexers
  • 4 CR1000s
  • 4 Instrument box
  • 4 charge controller (SS10)
  • 7 SW12V units
  • 12 HFP01s
  • 12 HydraProbe IIs

Supplies / Equipment IARC is providing to the project that will need to be replaced

  • Radios
    • set hopping channels to an alternate: 13
    • Network ID is 2279 (BARW on phone)
    • set up in multipoint mode
    • RF450 S/N 882-5337; 875-2691;875-2750
    • FGR S/N 873-7563 (Master); 873-5346
    • Need 2 more Null Modems 8/27/2012

Enroute

  • Battery Boxes should arrive 8/30ish
  • batteries I'm not sure of but should arrive near our departure.

Program to do yet

  • seasonal snow measurements... not going to do anything special I think.
  • test final program... testing.

Pre-trip to do

  • Cut Pipe
  • Ship stuff: thinking two loads
    • shipment 1 ship Wednesday and that will be stuff we'll need on arrival
    • shipment 2 ship Friday and that will be things still being prepped early next week.
  • Organize per site items
    • Precip Stand
      • 3 screed stakes
      • Pipe: 2 pcs 5 ft; 1 pcs 2.5'
      • Hose Clamps (2 sizes)
      • NuRail fittings (currently in Bob's office)
    • Tripod Related
      • 1 pcs tripod
      • 1 pcs instrument box & contents:
        • cable ties
        • AM16/32s
        • 2 pcs current excitation module
        • 1 pcs CR1000
        • 1 pcs radio & power cable
        • 1 pcs radio antenna setup
        • 1 pcs null modem
      • Energy system
        • 1 pcs solar panel
        • 2 pcs ubolts for solar panel mount
        • 2 pcs aluminum strips for solar panel mount
        • 4 pcs nuts & bolts for solar panel mount
        • Batteries if they arrive
        • Ring connectors for batteries
        • power cable to go between batteries
        • power cable to go battery box to instrument box
        • cable protection between battery box and instrument box
        • power cable to go between solar panel and battery box
        • cable protection to go between solar panel and battery box
        • cold temperature power cable (red & black or an all-weather extension cord)
        • 1 pcs power cable from solar panel
        • 1 pcs cable protection for solar panel cable (sort of left off cable protection estimates I'm thinking)
        • 1 pcs charge controller
      • 1 pcs SR50A setup
        • 5' x 3/4" Pipe
        • SR50A setup
        • 1 pcs SR50A
        • 1 pcs SR50A mount
        • 1 pcs SR50A cable
        • 1 pcs SR50A cable protection
      • Air Temperature Setup
        • 1 pcs AT radiation shield
        • 1 pcs 107 Temperature Probe
        • 1 pcs cable protection
      • Subsurface Hardware
        • 9 HydraProbe IIs
        • 3 HFP01 heat flux plates
        • 5 deep thermistor probes
        • 1 shallow thermistor probes
        • 9 thermistors probes to pair with the hydraprobe iis
        • 6 thermal conductivity probes to put two of the pits

Things to buy

  • Bit o' Food?
  • buy additional required hardware
  • 2400 ft of 3/4" flex conduit
  • 100 ft of 3/8" flex conduit
  • brown tarps (Freds)
  • solar panel mounts (Lowes)
  • wiring stuff (to control all the excess wires) Action Packers?
  • conduit, lots!
  • large pvc and fittings to go between action packer and CSI enclosure?
  • fittings for an additional opening in bottom of enclosures
  • cable ties
  • SDI cable extensions

Stuff to bring out

Extras from Bill

  • Heat shrink
  • Heat Gun


Other

  • Hole Saw for additional box holes (currently just a single hole) ... purchased and packed.


things not on a PR yet

  • power cables (reds & blacks or extension cords)
  • cable protection for energy system
  • brown tarps from Freddies
  • NRS straps maybe from the Beave for the tarp.
  • Cable Ties
  • Terminal strips

Equipment To Ship

  • 4 Tripods
  • 4 Battery Boxes
  • 4 Solar Panels
  • Thermistor Strings
  • Additional Thermistors
  • Radiation Shields
  • Instrument boxes with loggers etc. installed
  • charge controllers

Technical Gear

  • Shotgun
  • Keypad
  • fish tape
  • kayak
  • Tool Bags
  • Computer & (packed) SC32B
  • Climbing harness
  • Climbing Gear Proper
  • Serial Cables & spares
  • brown tarps
  • Sawzall
  • drill

Food to bring out

  • Optional

Probable Luggage

  1. Shotgun [Bob #1]
  2. Bob Personal backpack [Bob #2]
  3. Work Actionpacker #1 [Bob #3]

How it will go down out there

  • Bil & Vlad drill the thermistor bore holes
  • Bob focuses on the wiring and station set up with an assist as needed from others
  • Anna if she comes digs and logs soil pits
  • All will share hauling duties from truck to intensive site area