* First Program (not including thermal offsets which will be added onsite):  
 
* First Program (not including thermal offsets which will be added onsite):  
 
** https://github.com/frankohanlon/ngee/blob/master/ngee_intensive_site_subset.CR1
 
** https://github.com/frankohanlon/ngee/blob/master/ngee_intensive_site_subset.CR1
 
+
* [[NGEE September 3 2012 Trip not essential to the trip information]]
 
===Metadata type stuff===
 
===Metadata type stuff===
 
* [[NGEE-Barrow Calibration and Serial Numbers]]
 
* [[NGEE-Barrow Calibration and Serial Numbers]]
Line 13: Line 13:
 
* Batteries
 
* Batteries
 
** '''NAC Waybill 345-2130-8431'''
 
** '''NAC Waybill 345-2130-8431'''
 
===Supplies / Equipment the GIPL is providing to the project that will need to be replaced===
 
* 4 Tripods
 
* 4 CrossArms
 
* 4 Radiation Shields
 
* 4 107 Temperature Probes
 
* 24 Thermal Conductivity sensors from East30
 
* 8 Current Excitation Modules
 
* 8 AM16/32 Multiplexers
 
* 4 CR1000s
 
* 4 Instrument box
 
* 4 charge controller (SS10)
 
* 7 SW12V units
 
* 12 HFP01s
 
* 12 HydraProbe IIs
 
 
=== Supplies / Equipment IARC is providing to the project that will need to be replaced===
 
* Radios
 
** set hopping channels to an alternate: 13
 
** Network ID is 2279 (BARW on phone)
 
** set up in multipoint mode
 
 
** RF450 S/N 882-5337; 875-2691;875-2750
 
** FGR S/N '''873-7563 (Master)'''; 873-5346
 
** '''Need 2 more Null Modems''' 8/27/2012
 
  
 
===Enroute===
 
===Enroute===

Revision as of 15:31, 29 August 2012

Notes

Metadata type stuff

* PakBus IDs - A = 400; B = 401; C = 402; D = 403

Shipping

  • Tripods, battery boxes etc.
    • NAC Waybill 345-2130-8372
  • Batteries
    • NAC Waybill 345-2130-8431

Enroute

  • Battery Boxes should arrive 8/30ish
  • batteries I'm not sure of but should arrive near our departure.

Program to do yet

  • seasonal snow measurements... not going to do anything special I think.
  • test final program... testing.

Pre-trip to do

  • Cut Pipe
  • Ship stuff: thinking two loads
    • shipment 1 ship Wednesday and that will be stuff we'll need on arrival
    • shipment 2 ship Friday and that will be things still being prepped early next week.
  • Organize per site items
    • Precip Stand
      • 3 screed stakes
      • Pipe: 2 pcs 5 ft; 1 pcs 2.5'
      • Hose Clamps (2 sizes)
      • NuRail fittings (currently in Bob's office)
    • Tripod Related
      • 1 pcs tripod
      • 1 pcs instrument box & contents:
        • cable ties
        • AM16/32s
        • 2 pcs current excitation module
        • 1 pcs CR1000
        • 1 pcs radio & power cable
        • 1 pcs radio antenna setup
        • 1 pcs null modem
      • Energy system
        • 1 pcs solar panel
        • 2 pcs ubolts for solar panel mount
        • 2 pcs aluminum strips for solar panel mount
        • 4 pcs nuts & bolts for solar panel mount
        • Batteries if they arrive
        • Ring connectors for batteries
        • power cable to go between batteries
        • power cable to go battery box to instrument box
        • cable protection between battery box and instrument box
        • power cable to go between solar panel and battery box
        • cable protection to go between solar panel and battery box
        • cold temperature power cable (red & black or an all-weather extension cord)
        • 1 pcs power cable from solar panel
        • 1 pcs cable protection for solar panel cable (sort of left off cable protection estimates I'm thinking)
        • 1 pcs charge controller
      • 1 pcs SR50A setup
        • 5' x 3/4" Pipe
        • SR50A setup
        • 1 pcs SR50A
        • 1 pcs SR50A mount
        • 1 pcs SR50A cable
        • 1 pcs SR50A cable protection
      • Air Temperature Setup
        • 1 pcs AT radiation shield
        • 1 pcs 107 Temperature Probe
        • 1 pcs cable protection
      • Subsurface Hardware
        • 9 HydraProbe IIs
        • 3 HFP01 heat flux plates
        • 5 deep thermistor probes
        • 1 shallow thermistor probes
        • 9 thermistors probes to pair with the hydraprobe iis
        • 6 thermal conductivity probes to put two of the pits

Things to buy

  • Bit o' Food?
  • buy additional required hardware
  • 2400 ft of 3/4" flex conduit
  • 100 ft of 3/8" flex conduit
  • brown tarps (Freds)
  • solar panel mounts (Lowes)
  • wiring stuff (to control all the excess wires) Action Packers?
  • conduit, lots!
  • large pvc and fittings to go between action packer and CSI enclosure?
  • fittings for an additional opening in bottom of enclosures
  • cable ties
  • SDI cable extensions

Stuff to bring out

Extras from Bill

  • Heat shrink
  • Heat Gun


Other

  • Hole Saw for additional box holes (currently just a single hole) ... purchased and packed.


things not on a PR yet

  • power cables (reds & blacks or extension cords)
  • cable protection for energy system
  • brown tarps from Freddies
  • NRS straps maybe from the Beave for the tarp.
  • Cable Ties
  • Terminal strips

Equipment To Ship

  • 4 Tripods
  • 4 Battery Boxes
  • 4 Solar Panels
  • Thermistor Strings
  • Additional Thermistors
  • Radiation Shields
  • Instrument boxes with loggers etc. installed
  • charge controllers

Technical Gear

  • Shotgun
  • Keypad
  • fish tape
  • kayak
  • Tool Bags
  • Computer & (packed) SC32B
  • Climbing harness
  • Climbing Gear Proper
  • Serial Cables & spares
  • brown tarps
  • Sawzall
  • drill

Food to bring out

  • Optional

Probable Luggage

  1. Shotgun [Bob #1]
  2. Bob Personal backpack [Bob #2]
  3. Work Actionpacker #1 [Bob #3]

How it will go down out there

  • Bil & Vlad drill the thermistor bore holes
  • Bob focuses on the wiring and station set up with an assist as needed from others
  • Anna if she comes digs and logs soil pits
  • All will share hauling duties from truck to intensive site area