(Created page with "Just a skeleton of a beginning but wanted a place to collect scraps of ideas etc. ====To Do Yet==== * Helicopter Safety Plan * Renew Tracker plans for field season * Make su...")
 
Line 6: Line 6:
 
* Renew Tracker plans for field season
 
* Renew Tracker plans for field season
 
* Make sure GPS systems are compatible between groups
 
* Make sure GPS systems are compatible between groups
* Ship stuff
+
* PR for &  Ship stuff (to Nome Gnome?)
  
 +
===Snow Survey Gear===
 +
* 2x Thermal Conductivity Probes
 +
* 3x Snow density tube
 +
* 1x magnaprobe
 +
* Lots of ziplocs
 +
* snow scale
 +
 +
====To Purchase yet====
 +
* ziplocs
 +
* rebar
 +
 +
 +
====
 
====Itinerary====
 
====Itinerary====
  

Revision as of 15:33, 15 February 2017

Just a skeleton of a beginning but wanted a place to collect scraps of ideas etc.

To Do Yet

  • Helicopter Safety Plan
  • Renew Tracker plans for field season
  • Make sure GPS systems are compatible between groups
  • PR for & Ship stuff (to Nome Gnome?)

Snow Survey Gear

  • 2x Thermal Conductivity Probes
  • 3x Snow density tube
  • 1x magnaprobe
  • Lots of ziplocs
  • snow scale

To Purchase yet

  • ziplocs
  • rebar


==

Itinerary

3/20

  • Bob Busey & LANL Crew arrive in Nome
  • Hotel opens @ 3pm
  • pick up stuff from cargo
    • gear
    • safety equipment
  • groceries

3/21

  • Lily Cohen & Bob Bolton arrive in Nome
  • Hotel opens @ 3pm
    • get settled.
    • get groceries

Survey marker trip day:

  • 8am start
  • 10am arrive on-site and set up survey gps system
  • 10:45 snowmachine to the top of the drainage. Work down the hill deploying mark
  • ~7 hrs to deploy markers for UAV/helo
    • Stop sign
    • rebar protection
    • rebar
  • evening: return to Nome.

3/22

  • Begin snow surveys in Teller