Difference between revisions of "SS Site Visit 2021-10"

From IARC 207 Wiki
Jump to navigation Jump to search
Line 20: Line 20:
 
* Plugged in tipping bucket heater
 
* Plugged in tipping bucket heater
 
* Remove Forest Floor LI7200
 
* Remove Forest Floor LI7200
 +
* Swap Tower LI7200 (But need to update the calibration info still)
 
* Add an HDMI switch for monitor.
 
* Add an HDMI switch for monitor.
 +
* Swap out top 2 anemometers

Revision as of 13:57, 6 October 2021

Partial Task List

  • Ground anchor strengthening
  • finish tracking power
  • Replace CNR4s
  • replace the anemometers starting from top
  • pull out the eddy covariance units for recalibration
  • replace geonor water / ethanol / antifreeze
    • I have written on the a bucket the ratio. Also need to dilute the mix so I can drop at dump.
  • Hang the SWE sensor
  • Add the NL100 to the network
  • update the software
  • 12V battery backups
  • replace UPS batteries?

Activities

  • 2021-10-06 12:00 AK DT -- changed liquids in the geonor. 5 Liters antifreeze / 3 Liters ethanol / 1 bottle baby oil
    • Removed like 5.3 gallons
    • Re leveled stand, too.
  • Plugged in tipping bucket heater
  • Remove Forest Floor LI7200
  • Swap Tower LI7200 (But need to update the calibration info still)
  • Add an HDMI switch for monitor.
  • Swap out top 2 anemometers