Umiat May 2010 Field Trip

From IARC 207 Wiki
Revision as of 09:18, 12 April 2010 by imported>Eyoucha (→‎To DO for Field Prep)
Jump to navigation Jump to search

Umiat May 2010 Logistics

This website helps me organize everything that needs to get done for the Umiat logistics May 2010.

(EKY Last Update 4/12/10)

Schedule

  • April 12-17 Umiat Runway Plowed by UIC
  • May 1 - BLM flight full
  • May 4-7 ADCP/boating training, May 6 Sontek River Surveyor ADCP training event
  • May 8-9 DOT plow runway?
  • May 8-12 Richard to Umiat Daily BLM flights to Umiat, 1 UAF camp supplies flight 1 UAF staff flight 1 UAF equipment/gear flight?
  • May 11 BLM fuel bladders set up (?)
  • May 12 BLM fuel delivery (?)
  • May 9-11 Horst Camp to Umiat 2 caravan flights mobilization
  • May 11 or 12 UAF crew & Horst camp to Umiat (1 or 2 flights? Gear weight)
  • May 19 Ken to Umiat, Bob to Prudhoe (Dave B. to Umiat w/ BLM). Resupply Horst camp.
  • May 26 BLM Camp resupply flight (Bill Lee arrives)
  • June 3 UAF crew + cook departs Umiat, Horst group arrives for camp tear down
  • June 5 2 flights for Horst crew demob to Fairbanks

Logistics To DO

  • Book Wright Air Flights
  • Coordinate flights w/ BLM Richard
  • Assist with DEC permitting for Horst Camp as needed
  • UIC Quote - Bill
  • Horst camp weights (Josh Horst)
  • UAF equip weights
  • ADCP Q msmst cheat sheet Emily/Bob
  • Trimble GPS set up cheat sheet (Bill Lee)

To DO for Field Prep

  • Test ADCPs in river May 3-7
  • River Surveyor ADCP/GPS set up and testing in river May 3-7
  • Novatel GPS configuration files - Ken
  • Trimble memory upgrade and battery cable - Emily/Ken
  • Configure HOBO meters
  • Survival kits put together
  • Manuals/Guidance

Equipment/Supplies to Send to Umiat

  • 1 drum unleaded fuel for boat motor and misc. use
  • Spare Aquistar PTs
  • HOBO PTs + data reader
  • Wall tent supplies @ red door
  • 3- 12V 100 a-h batteries (ADCP, Trimble GPS, spare)
  • battery charger
  • Trimble GPS and tripod
  • ADCP Rio Grande
  • ADCP River Surveyor
  • Novatel GPS and wiring harnesses, config files
  • Big Toughbook
  • 2 radios
  • 2 GPS tripods
  • spare drybags
  • life jackets (2 to Itkillik, 2 to Chandler)
  • printer
  • Disc weights for PTs
  • Hose clamps
  • sledgehammers
  • rebar drive head
  • level, survey tripod, rod
  • backup hardrives
  • flow tracker, rod, manuals
  • binoculars
  • laser rangefinder
  • helo helmets
  • Satellite phones (2)
  • Shotguns + ammo (2)
  • spare boat & motor parts
  • survival/safety bags
  • misc. stream gauging parts
  • Manuals/Guidance

Summary Field work To Do List

  • Measure snowmelt discharge in Anaktuvuk River
  • Improve existing (2009) rating curve (i.e., stage/discharge relationship) for Anaktuvuk River gauging station
  • Evaluate/maintain and repair stations on Anaktuvuk, Itkillik, and Chandler rivers
    • Chandler Camerea
    • Chandler PTs, Station
  • Find new location for Chandler Station?
  • Take basic hydrologic/ice observations for each river