2017 NGEE Nome October trip
- Car Rental Reservation: R41747
- 9/29 - 10/6
- Nugget reservation 1346
Activities:
- Nome
- find new base station location with Chad
- return GCI cable modem from Boxer Apartments
- teller
- move snow poles to TLA line
- put one snow pole in each actual snow course center of X for the IS crosses.
- remove remaining poles
- teller top:
- double-check data
- thermal conductivity probes working?
- maybe replace cnr4
- and or drill out stripped screws
- replace memory card in camera
- teller bottom
- replace memory card in camera
- sr50a transducer replacement, 2x
- remove 1 PT
- discharge measurement
- Kougarok m64
- bring guy wire markers for K64 met station (at uaf storage)
- setup snow grid for spring (surveying)
- 9/25 waiting on geopdf & shape files from Lauren for this.
- survey the remaining intensive sites out there:
- IS5, IS6, IS8
- soil pit.............
- altar shield
- need 2 2x4 chunks for base
- need 2 more pieces of functional altar shield
- need wood screws to screw vertical pipes to base.
- Original Kougarok:
- download data by radio
- Council
- fix program at C1 Grid
- download C2 blueberry data over radio
Loose Itinerary
- 9/29 (8:18 - 9:36 Twilight to twilight)
- evening: arrive & stay in apartments
- 9/30 (8:21 - 9:19)
- take some storage stuff to dump
- evening: Lily arrives
- stay in hotel
- 10/1 (8:24 - 9:16)
- Teller
- walk the end point of the lines set up in March 2017 and remove the orange poles
- place 4 poles at bottom to help outline location of channel for PTs
- 10/2 (8:27 - 9:12)
- Teller Top:
- change desiccant which will require:
- drill
- drill bit
- tap & die
- replacement machine screws for stripped out ones.
- change desiccant which will require:
- Teller button up for winter, snow pole remainder
- remove one PT at the bottom site
- Teller Top:
- 10/3 (8:30 - 9:09)
- drive to kougarok. download data over radios from K sites
- stretch goal... visit k2 if time for thaw depth measurements
- 10/4 (8:33 - 9:05)
- kougarok m64 winter button up
- ??? soil pit ???
- kougarok m64 finish surveying & deploy snow poles
- 10/5 (8:36 - 9:02)
- Council
- survey 2017 plots?
- download data over radio for C2 (at minimum)
- visit C2?
- fix program at C1
- 10/6 depart