2018
- More PAR sensors and hardware for in-situ
- Buy another SI-111 SDI12 model
- Attend LI-COR training?
- Polish Battery Backup System
- replace Loggernet computer
- bring out an NL100 or USB to serial adapter
- Submit PRs for Summer 2018 Instrument Recalibrations
- Vaisala HMP155s
- MetOne 010C
- Kipp & Zonen CNR4
- Late Fall recalibrations:
Ss soil has room on c7 for sdi12 rest or sr50a are on c3, c4 is open for other stuff. Just moved cs616 to 5v to see if that does anything. Need to confirm this doesn't mess up and create noise in signals.
- Replace SR50A transducers
- Dig second pit for soil instruments
- clean up outdoor power cords
- waterproof a bit some of the tower blowers (might be as easy as more cable ties / tape to keep the white box deals right side up.
- I brought out a collection of one and two hole deals for securing loose cabling here and there in and out of the shed. That could be sorted out.
- connect those shop power strips and get one more for inside?
- SI111 install
- buy and add more PAR top and bottom (4x and matching hardware)
- add another tipping bucket.