SS Site Visit 2021-10
Partial Task List
- Ground anchor strengthening
- finish tracking power
- Replace CNR4s
- replace the anemometers starting from top
- pull out the eddy covariance units for recalibration
- replace geonor water / ethanol / antifreeze
- I have written on the a bucket the ratio. Also need to dilute the mix so I can drop at dump.
- Hang the SWE sensor
- Add the NL100 to the network
- update the software
- 12V battery backups
- replace UPS batteries?
Activities
- 2021-10-06 12:00 AK DT -- changed liquids in the geonor. 5 Liters antifreeze / 3 Liters ethanol / 1 bottle baby oil
- Removed like 5.3 gallons
- Re leveled stand, too.
- Plugged in tipping bucket heater
- Remove Forest Floor LI7200
- Swap Tower LI7200 (But need to update the calibration info still)
- Add an HDMI switch for monitor.
- Swap out top 2 anemometers