Schedule

  • April 12-17 Umiat Runway Plowed by UIC
  • May 1 - BLM flight full
  • May 4-7 ADCP/boating training, May 6 Sontek River Surveyor ADCP training event
  • May 8-9 DOT plow runway?
  • May 8-12 Richard to Umiat Daily BLM flights to Umiat, 1 UAF camp supplies flight 1 UAF staff flight 1 UAF equipment/gear flight?
  • May 11 BLM fuel bladders set up (?)
  • May 12 BLM fuel delivery (?)
  • May 9-11 Horst Camp to Umiat 2 caravan flights mobilization
  • May 11 or 12 UAF crew & Horst camp to Umiat (1 or 2 flights? Gear weights?) Bob, Jeff, Jeff, Horacio
  • May 12 UAF Helicopter arrives in Umiat
  • May 19 Ken to Umiat, Bob to Prudhoe (Dave B. to Umiat w/ BLM). Resupply Horst camp.
  • May 26 BLM Camp resupply flight (Bill Lee arrives)
  • June 3 UAF crew + cook departs Umiat, Horst group arrives for camp tear down
  • June 5 2 flights for Horst crew demob to Fairbanks

Logistics To DO

  • Book Wright Air Flights
  • Coordinate flights w/ BLM Richard
  • Assist with DEC permitting for Horst Camp as needed - Emily
  • UIC Quote - Bill
  • Horst camp weights (Josh Horst)
  • UAF equip weights - Jeff M?
  • ADCP Q msmst cheat sheet - Emily/Bob
  • Trimble GPS set up cheat sheet - Bill Lee

To DO for Field Prep

  • Shopping List
  • Test ADCPs in river May 3-7
  • River Surveyor ADCP/GPS set up and testing in river May 3-7
  • Novatel GPS configuration files
  • Trimble memory upgrade and battery cable
  • Configure HOBO meters
  • Survival kits put together
  • Manuals/Guidance
  • Helicopter time tracking sheet

Equipment/Supplies to Send to Umiat

  • 1 drum unleaded fuel for boat motor and misc. use
  • Spare Aquistar PTs
  • HOBO PTs + data reader, hardware
  • Wall tent supplies @ red door
  • 3- 12V 100 a-h batteries (ADCP, Trimble GPS, spare)
  • battery charger
  • Trimble GPS and tripod
  • ADCP Rio Grande
  • ADCP River Surveyor
  • Novatel GPS and wiring harnesses, config files
  • Big Toughbook
  • 2 radios
  • 2 GPS tripods
  • Mount for GPS reciever on boat (from USV)
  • spare drybags
  • life jackets (2 to Itkillik, 2 to Chandler)
  • box for lifejacket storage
  • printer
  • Disc weights for PTs
  • Hose clamps
  • sledgehammers
  • rebar drive head
  • level, survey tripod, rod
  • backup hardrives
  • flow tracker, rod, manuals
  • binoculars
  • laser rangefinder
  • helo helmets
  • Satellite phones (2)
  • Shotguns + ammo (2)
  • pepper spray
  • gun cleaning kit
  • anchor
  • boat entry rope
  • spare boat & motor parts
  • boat motor manuals
  • survival/safety bags
  • misc. stream gauging parts
  • Manuals/Guidance

Summary Field work To Do List

  • Measure discharge as frequently as possible in Anaktuvuk River during snowmelt runoff
  • Evaluate/maintain and repair stations on Anaktuvuk, Itkillik, and Chandler rivers
    • Chandler Camera
    • Chandler PTs, Station
  • Find new location for Chandler Station?
  • Take basic hydrologic/ice observations for each river
  • Improve existing (2009) (i.e., stage/discharge relationship) for Anaktuvuk River gauging station when ice-free
  • Anaktuvuk Rating Curve / Anaktuvuk Rating Curve - Log (Last Update: 3/29/10, EKY)