NGEE Barrow 2013 Site Install Trip
Revision as of 20:32, 11 April 2013 by 74.124.101.171 (talk)
Contents
Shipping
- New Instrumentation once it arrives:
- Precip Buckets 3x
- Wind Screen 3x
- HMP155s 6x
- MetOne 5x
- Barometric Pressure
- Leg Mount Instrument Boxes 3x
- Install AM16/32B if time
- Install SDM Switch if time
- Radiation Shields
- Cross Arms
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
- 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
- Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
To Add to each site
- 2 HMP155s w/ Radiation Shields
- 2 Met One WS (only one for Site A)
- 1 Tipping Bucket w/ Windscreen
- 1 CNR4 Net Radiometer with Heater/Fan Control
- 1 Leg Mounted Enclosure
- 1 SDM Based IO Expander
- 1 AM16/32
Additionally, to add to Site A
- CS106 Barometric Pressure
- RM Young Anemometer
To Do as of 4/10/2013
- Modify Programs
- Wiring Diagrams
- PRs for freight
- Sketch up site
- Wire up boxes as much as possible (is anything possible? Maybe just mount the peripherals)
- cut crossarms to length
Remaining things to grab
- ?
To Purchase
- ?
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand (3 sets)
- 4 NuRail 3/4 offset cross pieces
- 1 Novalynx Wind Screen
- 1 TE525m & Cable
- Precip Stand (3 sets)
- Tripod Related
-
- Tripod Related
Things to buy
- Bit o' Food?
- ?
Stuff to bring
things not on a PR yet
Technical Gear
- Shotgun
- Keypads
- fish tape
- Tool Bags
- Computer & (packed) SC32B
- Climbing harness
- Climbing Gear Proper
- Serial Cables & spares
- Sawzall
- drill
Food to bring out
- Optional
Probable Luggage
- Shotgun [Bob #1]
- Bob Personal backpack [Bob #2]
- Work Actionpacker #1 [Bob #3]
Rough on-site todo
- Remove box & solar panel
- Measure from top of tripod base to cross arm... note in fieldbook
- Remove crossarm off tripod
- unscrew center pole
- put 1.5" offset nurail fitting on new center pole
- attach new center pole
- put cross arm, instrument box, and solar panel back on the tower.
- Install new instrument box on lower leg.
- Mount all new sensors
- Net Radiometer @ 1-1.5m
- WS on radiometer crossarm
- HMP155 on radiometer crossarm
- Second HMP155 & WS high up on tower, maybe as high as they'll reach.
- Armor all the cabling
- Armor and install the precip bucket.
- Install the precip wind screen
- send new program to data logger