NGEE Barrow 2013 Site Install Trip 2
Revision as of 15:41, 10 June 2013 by 137.229.92.213 (talk)
Contents
June 2013 Trip
Shipping
- New Instrumentation once it arrives on 5/26ish:
- Precip Buckets 3x
 - Wind Screen 3x
 - HMP155s 6x
 - MetOne 6x
 - Barometric Pressure
 - Radiation Shields
 - Cross Arms & Mounts
- 1.5" Sched 40 Aluminum = Net Radiometer 3x
 - 1" Sched 40 Aluminum = Upper WS & AT/RH 3x
 
 - Tripod Mast
- 1.5" Sched 40 Galvanized Pipe
 
 - Net Radiometer
- Fan/Heater is in Barrow
 
 - NuRail Fittings for crossarms
 
 
To Add to each site
- 2 HMP155s w/ Radiation Shields
 - 1 pcs 107 radiation shield (bringing it, will mull when looking at as-built.
 - 2 Met One 014a WS
 - 3pcs Cross Arm Mounts for each
- 3.5m cross arm
 - 3.5m WS
 - 1m WS
 
 - 1 Tipping Bucket w/ Windscreen
- Some alter-shield NuRail fittings are on site. Check the battery box I think?... also may have been repurposed for snow sensors, my notes are unclear. Also check the D site box in storage.
 
 - 1 CNR4 Net Radiometer with Heater/Fan Control
 - 1 AM16/32B inside the box
 - Cable Management inside the box (new cable list:)
- 2 pcs 014a
 - 2 pcs hmp155
 - 3 pcs cnr4
 
 - might go looking for a short steel cable of some sort to run down the pipe.
 - Anything else?
 
Additionally, to add to Grid Site
- Maybe?  Still on the fence about this due to ground location of the box.  CS106 Barometric Pressure.  Could also add to A yet.
- Need to dig out a vent tube
 - Bring up parts to put a new hole in this enclosure
 
 
Rewiring at each site
- Move AM16/32B #1 & #2 RES to CR1000 C1
 - Move SR50A Green Wire to CR1000 C5
- Reprogram the IDs for the SR50As
- #1 = ID7
 - #2 = ID8
 - #3 = ID9
 
 
 - Reprogram the IDs for the SR50As
 - XX Also Measure Thermal Conductivity Heater Values
 - XX Bring up 3 resistors for CNR4 Thermistor measurement
 
To Do as of 6/8/2013
- Wiring Diagrams
 - Sketch up site
 - holes in box for instrumentation maybe?
 - cut crossarms to length (in Barrow)
 - Change SDI-12 IDs for SR50As (in Barrow)
 - Copy B program additions to A & C
 
Remaining things to grab
- XXX Nu Rail oddball connectors from cabinet
 - XXX BP tubing for grid site
 - --> Cord Grips for grid site
 - XXX silicone for grid site
 
To Purchase
- XX More Flexible Conduit
 - XX Vent Tube
 - Cable Management supplies
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand  (3 sets)
- XX 4 NuRail 3/4 offset cross pieces
 - XX 1 Novalynx Wind Screen
 - XX 1 TE525m & Cable
 
 
 - Precip Stand  (3 sets)
 
- Tripod Related
- XX 1.5" Aluminium cross arm for CNR4, lower AT/RH & WS
 - XX 1.5" Nurail offset
 - XX 1" Aluminum cross arm for upper AT/RH & WS
 - XX HMP155s, cables, Radiation Shield
 - XX 014a WS, cables, nurail / cross arm mounts
 
 
- Tripod Related
 
Things to buy
- Bit o' Food?
 - 1.5" Pipe Threader
 - Flex Conduit
 
Stuff to bring
Technical Gear
- Keypads
 - XX fish tape
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Serial Cables & spares
 - XX Sawzall
 - XX drill
 - XX Pipe Wrench
 - 1.5" Pipe Threader
 
Food to bring out
- Optional
 
Rough on-site todo (for each site)
- Measure from top of tripod base to cross arm... note in fieldbook
 - Remove box & solar panel from tripod mast
 - Remove existing crossarm off tripod
 - unscrew center pole
 - put 1.5" offset nurail fitting on new center pole
 - add top of tower cross arm with anemometer & HMP155
- Armor and secure these two cables
 
 - screw on the new center pole
 - put the existing cross arm, instrument box, and solar panel back on the tower.
 - Mount all new sensors
- On lowest crossarm, 1-1.5m above ground surface
- Net Radiometer
 - Cross Arm bracket
- Wind Speed
 
 - HMP155 on radiometer crossarm
 
 - Armor all the cabling lower cabling
 - Armor and install the precip bucket.
 - Install the precip wind screen
 
 - On lowest crossarm, 1-1.5m above ground surface
 - send new program to data logger
- Bring cabling into the box and wire into the appropriate data logger / multiplexer.
 
 
Idealized Rough Itinerary (with dates to float depending on how long things take)
I budgeted 2 days per site but I'm hoping 1 to 1.5 days is more realistic.
6/11
- Fly to Barrow
 - Sort Shipped Gear
 - Track down a sled
 - Organize stuff locally in Barrow
 - Quick trip to the sites if there is time
 - Look at D site box for parts (and prepare for shipment back to Fairbanks)
 
6/12
- Haul stuff out for A site
 - Add components to A site
 
6/13
- Haul stuff out for B site
 - Finish A site
 - Start B site
 
6/14
- Haul stuff out for C site
 - Finish B site
 - Start C site?
 
6/15
- Finish C site
 
6/16
- Ship stuff back to Fairbanks
 - Depart for Fairbanks