NGEE Barrow 2013 Site D Install Trip August 2013
Revision as of 16:33, 6 August 2013 by 137.229.92.251 (talk)
Goals:
- Install Barrow Site D Inventory
 - Soil Cores
 
Soil Core component: 8 Bob, Bob, & Sammy
- Use RTK GPS and transect across a polygon in the area south
 - pull a
 
Site D Install Instrumentation List:
- 5 Temperature Probes (1.5m depth)
 - Possibly one soil pit (soil & water conditions depending)
 - Air Temperature / Relative Humidity @ 1.5 meters
 - Snow Depth @ 1.5 meters
 - Net Radiation @ 1.3 meters
 
Additional Site Work:
- Level Radiometers at the other sites
 - Change out the SR50A snow transducers for the existing stations (7pcs)
 - Change out the pipe for the snow stands (4 pcs)
 - Cable Extensions for Thermal Conductivity sensors @ C site
 - small enclosure & extra logger/MD485 for C site bonus thermal conductivity sensors
 - sledge tower feet
 
Additional Soil Work:
- At least 2 soil pits (soil to fill two coolers)
 
To Purchase:
- Terminal male adapter for PVC down pipe
 - Terminal lockring
 - Pipe for snow sensor stands
 - Pipe for D tripod
 - solar panel & mounting system
- flat stock
 - ubolts
 
 - bolts for Net Radiometer NuRail fitting
 - vertical pipe for Net Radiometer
 - Gauntlet Gloves
 
Odd Tools:
- Laptop
- serial cable
 - laptop weather resistant housing
 
 - tool bags
 - pipe wrench
 - drill for precip bucket screws
 - an additional wheelbarrow?
 - 2 coolers
 - GPS system
 
Finalize Program Wiring (thermistor vs. thermocouple for the thermal conductivity probes)
Itinerary: 8/19 Bill, Vlad, Bob Busey & Bob Bolton fly out
- Pick up gear and get ready to haul it out:
- tower
 - batteries
 - battery box
 - solar panel
 
 - sledge tower feet
 - haul stuff out by wheel barrow
 - instrumentation
 - shovel
 - coolers (2-3)
 - 
- 2
 
 - Program
 
Tasks:
- Put up tripod
- grab 4 pieces of trail mat from the NGEE conex
 - set up tripod with
 
 
Additional Maintenance:
- Self-tapping screws for precip lids
 - proper pipe for snow stands from 2012 install
 - replace transducers in SR50As -- 7 pcs
 - duct seal remaining holes in the enclosures
 
To purchase:
- Solar Panel
 - Charge controller?
 - Additional CSI stuff
- SR50A transducers
 - cross arm brackets
 
 - 1 inch aluminum cross arm (for Bill stock and D site)
 - duct seal
 - Fresh Desiccant for all sites
 
To Prep:
- wire up data logger box
 
Bring Survey GPS north
- emailed for a quote on R8 internal radio tuned to 418 MHz.