Super Site Activity Log
Revision as of 09:02, 5 October 2016 by 74.124.99.189 (talk)
Activity Log
- 8/29
- re-routed all radiation sensors & temporary rewire
 - powered off AT/RH
 - the cnr4 heater/ventilators are off at the moment.... might be a good time to shorten up the cables to them, too...
 
 - 9/1
- re-routed at/rh
 - hauled out bulk of tower clamps & related hardware
 
 - 9/18-9/28
- tracking down pipe & vehicles
 - fleshing out the procedure
 
 - 9/29
- three of four pipes temporarily mounted
 - fourth up
 - screwed in a couple more earth anchors
 
 - tinkered with boardwalk
 - 9/30 & 10/3
- focused on pipes SE, SW, NW pipes
 
 - 10/4
- removed original helper structure and replaced with permanent structure
 - added NE pipe
 - wrapped up earth anchor stuff
 
 - 10/5
- start on guy wires