2017 NGEE Nome October trip
Revision as of 12:09, 7 September 2017 by 137.229.92.185 (talk)
Activities:
- teller top:
- double-check data
- thermal conductivity probes working?
- maybe replace cnr4
- teller bottom
- sr50a transducer replacement, 2x
- remove 1 PT
- discharge measurement
- Kougarok m64
- bring guy wire markers for K64 met station (at uaf storage)
Loose Itinerary
- 9/29
- evening: arrive & stay in apartments
- 9/30
- Teller Snow pole survey & replacement
- put gps base at new location at bottom
- walk the end point of the lines set up in March 2017 and secure the orange poles so they are erect for winter.
- 10/1
- Teller button up for winter, snow pole remainder
- remove one PT at the bottom site
- 10/2
- drive to kougarok. download data over radios from K sites
- stretch goal... visit k2 if time for thaw depth measurements
- 10/3
- kougarok m64 winter button up
- soil pit
- kougarok m64 finish surveying
- 10/4
- Council
- survey 2017 plots?
- download data
- visit C2?
- 10/5 depart