SS Site Visit 2021-10
Partial Task List
- Ground anchor strengthening
 - finish tracking power
 - Replace CNR4s
 - replace the anemometers starting from top
 - pull out the eddy covariance units for recalibration
 - replace geonor water / ethanol / antifreeze
- I have written on the a bucket the ratio. Also need to dilute the mix so I can drop at dump.
 
 - Hang the SWE sensor
 - Add the NL100 to the network
 - update the software
 - 12V battery backups
 - replace UPS batteries?
 
Activities
- 2021-10-06 12:00 AK DT -- changed liquids in the geonor.  5 Liters antifreeze / 3 Liters ethanol / 1 bottle baby oil
- Removed like 5.3 gallons
 - Re leveled stand, too.
 
 - Plugged in tipping bucket heater
 - Remove Forest Floor LI7200
 - Add an HDMI switch for monitor.