NGEE September 3 2012 Trip
		
		
		
		
		
		
		Jump to navigation
		Jump to search
		
		
		
		
		
		
		
	
Contents
Notes
- NGEE Barrow Intensive Sites Initial Wiring
 - First Program (not including thermal offsets which will be added onsite):
 - NGEE September 3 2012 Trip not essential to the trip information
 
Metadata type stuff
- NGEE-Barrow Calibration and Serial Numbers
 - Thermistor Probe Calibrations ([1])
 - Thermistor Strings and Triple Calibrations ([2])
 - Timezone - UTC
 
* PakBus IDs - A = 400; B = 401; C = 402; D = 403
Shipping
- Tripods, battery boxes etc.
- NAC Waybill 345-2130-8372
 
 - Batteries
- NAC Waybill 345-2130-8431
 
 
Bill Remaining things to grab
- 2 pcs Null Modem cables
 - Heat shrink
 - Heat Gun
 - lead weights
 - 2 drill kits
 - 2 drills and batteries and chargers
 - small tarp for soil pits
 - frame pack
 
Bob Remaining things to grab
- 1 pcs SW12V Unit
 - 4 pcs nuts & bolts for solar panel mount
 - Grabbed, not packed
- 5 pcs radio & power cable
 - 5 pcs radio antenna setup
 - 3 pcs null modem
 - Ring connectors for batteries
 - power cable to go between batteries
 - power cable to go battery box to instrument box
 - hole drilling stuff for liquid-tite
 - Multiplexer wiring wire
 - Metal Tags for labeling
 
 
To Purchase
- Right size hole saw for the liquid-tite (for a 1/2" fitting)
 
Pre-trip to do
- Organized per site items (X means it's packed / shipped)
- Precip Stand
- X 3 screed stakes
 - X Pipe: 2 pcs 5 ft; 1 pcs 2.5'
 - X Hose Clamps (2 sizes)
 - X NuRail fittings
 
 - Tripod Related
- X 1 pcs tripod & cross arm
 - X 1 pcs instrument box & contents:
- X cable ties
 - X 2pcs AM16/32s
 - X 2 pcs current excitation module
 - X 1 pcs CR1000
 - 1 pcs radio & power cable
 - 1 pcs radio antenna setup
 - 1 pcs null modem
 
 - Energy system
- X 1 pcs solar panel missing one
 - X 2 pcs ubolts for solar panel mount
 - X 2 pcs aluminum strips for solar panel mount shipped in 4' sections in one of the tripod boxes
 - 4 pcs nuts & bolts for solar panel mount need to grab yet
 - X Batteries
 - X Ring connectors for batteries
 - power cable to go between batteries
 - X power cable to go battery box to instrument box
 - X cable protection between battery box and instrument box
 - X power cable to go between solar panel and battery box
 - X cable protection to go between solar panel and battery box
 - X cold temperature power cable (red & black or an all-weather extension cord)
 - X 1 pcs power cable from solar panel
 - X 1 pcs cable protection for solar panel cable (sort of left off cable protection estimates I'm thinking)
 - X 1 pcs charge controller
 
 - X 1 pcs SR50A setup
- SR50A setup
 - X 1 pcs SR50A
 - X 1 pcs SR50A mount (in tripod box)
 - X 1 pcs SR50A cable
 - X 1 pcs SR50A cable protection
 
 - Air Temperature Setup
- X 1 pcs AT radiation shield
 - X 1 pcs 107 Temperature Probe
 - X 1 pcs cable protection
 
 - Subsurface Hardware
- X 9 HydraProbe IIs
 - X 3 HFP01 heat flux plates
 - X 5 deep thermistor probes
 - X 1 shallow thermistor probes
 - X 9 thermistors probes to pair with the hydraprobe iis
 - X 6 thermal conductivity probes to put two of the pits
 
 
 
 - Precip Stand
 
Things to buy
- Bit o' Food?
 - buy additional required hardware
 - wiring stuff (to control all the excess wires) Action Packers?
 
Stuff to bring
things not on a PR yet
Technical Gear
- Shotgun
 - Keypad
 - fish tape
 - kayak
 - Tool Bags
 - Computer & (packed) SC32B
 - Climbing harness
 - Climbing Gear Proper
 - Serial Cables & spares
 - brown tarps
 - X Sawzall
 - drill
 
Food to bring out
- Optional
 
Probable Luggage
- Shotgun [Bob #1]
 - Bob Personal backpack [Bob #2]
 - Work Actionpacker #1 [Bob #3]
 
How it will go down out there
- Bil & Vlad drill the thermistor bore holes
 - Bob focuses on the wiring and station set up with an assist as needed from others
 - All will share hauling duties from truck to intensive site area