[[2018 NGEE Nome September Trip]]  | [[2018 NGEE Nome September Trip]]  | ||
* SR50A transducer replacement (fall activity)  | * SR50A transducer replacement (fall activity)  | ||
| − | * bring out one step stool to level teller bottom radiometer.  | + | * (2019) bring out one step stool to level teller bottom radiometer.  | 
| − | * bring out tap, die, drill, drill bit, screw for teller bottom radiometer.  | + | * (2019) bring out tap, die, drill, drill bit, screw for teller bottom radiometer.  | 
** screw...  | ** screw...  | ||
* '''also replace cnr4 desiccant since the unit didn't look like it was sealing right with this missing screw.'''  | * '''also replace cnr4 desiccant since the unit didn't look like it was sealing right with this missing screw.'''  | ||
* '''Bring out additional desiccant? for box'''  | * '''Bring out additional desiccant? for box'''  | ||
* '''Teller SW desiccant replacement'''  | * '''Teller SW desiccant replacement'''  | ||
| − | * Redrill hole for C1 Grid temperature probe  | + | * (2019) Redrill hole for C1 Grid temperature probe  | 
** what is needed for this?  | ** what is needed for this?  | ||
* Measure Creek Flow  | * Measure Creek Flow  | ||
| − | ** salt slug, n=  | + | ** salt slug, n=2 samples of 50g / known volume of water  | 
* Re-level radiometers  | * Re-level radiometers  | ||
| + | * polish radiometer domes  | ||
* Measure thermistors resistances at Teller Bottom and add them to fieldbook.  | * Measure thermistors resistances at Teller Bottom and add them to fieldbook.  | ||
** There are a couple with a 0.5C offset at spring freezing point so I think they may be failing and or something...  | ** There are a couple with a 0.5C offset at spring freezing point so I think they may be failing and or something...  | ||
| Line 25: | Line 26: | ||
* 6/11/2018 In Fairbanks... down in 106 / the basement there is a box of 12" nails.  Would be good to grab three for the Teller SW solar panel tripod  | * 6/11/2018 In Fairbanks... down in 106 / the basement there is a box of 12" nails.  Would be good to grab three for the Teller SW solar panel tripod  | ||
* I should do some experiments with the thermal conductivity thermistors in office/lab to see if I can reduce the noisiness.  | * I should do some experiments with the thermal conductivity thermistors in office/lab to see if I can reduce the noisiness.  | ||
| + | * finish surveying vegetation plots  | ||
====Kougarok====  | ====Kougarok====  | ||
| − | *   | + | * bring out a serial cable for box (removed it in fall 2018)  | 
| + | * get a compass reading on anemometer  | ||
| + | ** leave a compass in the box  | ||
====Teller SW Flow====  | ====Teller SW Flow====  | ||
| − | + | * left a metal meter stick at the site  | |
| − | |||
| − | |||
| − | |||
| − | |||
* fieldbook  | * fieldbook  | ||
* YSI conductivity meter  | * YSI conductivity meter  | ||
** manual  | ** manual  | ||
* electrical tape  | * electrical tape  | ||
| − | |||
==== Radiation Level:====  | ==== Radiation Level:====  | ||
| Line 45: | Line 44: | ||
* a bit of wood to provide better base for step ladder  | * a bit of wood to provide better base for step ladder  | ||
* phillips screwdriver for level  | * phillips screwdriver for level  | ||
| + | |||
==== Radiation Desiccant Swap:====  | ==== Radiation Desiccant Swap:====  | ||
Revision as of 12:23, 29 September 2018
Contents
To Buy
- Step ladder for teller bottom
 - 12 volt Trimble cable
 
Seward Peninsula
- SR50A transducer replacement (fall activity)
 - (2019) bring out one step stool to level teller bottom radiometer.
 - (2019) bring out tap, die, drill, drill bit, screw for teller bottom radiometer.
- screw...
 
 - also replace cnr4 desiccant since the unit didn't look like it was sealing right with this missing screw.
 - Bring out additional desiccant? for box
 - Teller SW desiccant replacement
 - (2019) Redrill hole for C1 Grid temperature probe
- what is needed for this?
 
 - Measure Creek Flow
- salt slug, n=2 samples of 50g / known volume of water
 
 - Re-level radiometers
 - polish radiometer domes
 - Measure thermistors resistances at Teller Bottom and add them to fieldbook.
- There are a couple with a 0.5C offset at spring freezing point so I think they may be failing and or something...
 - Related: I'm wondering if the delay between measurements should be increased for the thermistor measurements.
 - Also related: perhaps add a second string up at teller top?
 - sort of some additional homework is that I saw instability in a number of thermistors when measuring up top. I suspect but haven't verified that this instability is an indicator for the wonky temperatures seen in the data but need to confirm.
 
 - 6/11/2018 In Fairbanks... down in 106 / the basement there is a box of 12" nails. Would be good to grab three for the Teller SW solar panel tripod
 - I should do some experiments with the thermal conductivity thermistors in office/lab to see if I can reduce the noisiness.
 - finish surveying vegetation plots
 
Kougarok
- bring out a serial cable for box (removed it in fall 2018)
 - get a compass reading on anemometer
- leave a compass in the box
 
 
Teller SW Flow
- left a metal meter stick at the site
 - fieldbook
 - YSI conductivity meter
- manual
 
 - electrical tape
 
Radiation Level:
- step ladder
 - a bit of wood to provide better base for step ladder
 - phillips screwdriver for level
 
Radiation Desiccant Swap:
- Step ladder
 - small CSI phillips
 - K&Z desiccant pack
 - anti-corrosion goo
 
Teller Top Soil Temperatures
- Volt meter
 - fieldbook
- learned but need to confirm that the thermistors with a capacitance are ones that are unstable and failing.
 
 
Utqiagvik
- Intensive Site A HMP155 failed (3.5m)
 - Intensive Site B HMP155 failed (1.4m)
 - Intensive Site C HMP155 failed
 - need to replace the network cable running from the computer to the network switch. It cuts out with minimal bumping.... but station is finally back online!!!
 - Site A SR50A transducers have failed
 - some subsurface items are beginning to fail.
 - bring up clear tape and a biz card to label the computer
 - bring up the nuc plate and wood screws and other screw packet to mount nuc to wall