Visited 9/12 and 9/14
 
* Check out 1m AT/RH
 
* Check out 1m AT/RH
 +
** 9/14 replaced with borrowed unit from toolik
 
* Bring out battery for UPS system
 
* Bring out battery for UPS system
 +
** double-check battery voltages next time out.
 
* toughbook
 
* toughbook
* replacement WS sensors
+
* replaced bottom two wind sensors with new units
 +
* sending old units for recalibration
 
* Tour with Go
 
* Tour with Go
 
* put small toughbook on UPS system
 
* put small toughbook on UPS system
*
+
* 9/14 changed all MD485s at site to Pakbus protocol rather than transparent to see if this helps with data retrieval using python.
 +
* worked a bit on boardwalk
 +
* pounded in grounding rod
 +
* hooked second laptop to UPS

Latest revision as of 12:21, 14 September 2017

Visited 9/12 and 9/14

  • Check out 1m AT/RH
    • 9/14 replaced with borrowed unit from toolik
  • Bring out battery for UPS system
    • double-check battery voltages next time out.
  • toughbook
  • replaced bottom two wind sensors with new units
  • sending old units for recalibration
  • Tour with Go
  • put small toughbook on UPS system
  • 9/14 changed all MD485s at site to Pakbus protocol rather than transparent to see if this helps with data retrieval using python.
  • worked a bit on boardwalk
  • pounded in grounding rod
  • hooked second laptop to UPS