  • pipe
  • 2 pieces of 5ft w/
  • 6pcs -- 1.5" x 1/4-20 bolts for
  • should refresh on the pin outs for the iridium.


Station Tripod setup:

  • survey tripod
  • 1 pcs 1/2 height unistrut bolted to survey tripod using:
    • 2 pcs 1/4" fender washer
    • 2pcs 1/4" unistrut nut deals
    • 2 pcs 1.5" x 1/4-20 bolts
  • 1" horizontal pipe cut to 2 5' sections and coupled in middle
  • secure horizontal pipe to unistrut using two u-bolts

To buy for tripod station:

  • 2 pcs 10' x 1" stick of conduit for horizontals
  • 2 pcs 10' x 3/4" metal conduit for verticals
  • 2 pcs 2" dia x 3" long x 5/6" u-bolt (stainless preferred)
  • 6 pcs -- 1.5" x 1/4-20 bolts

Prep work still to go:

  • finalize survival stuff