2022 NGEE Nome October Trip
Jump to navigation
Jump to search
Items for October Trip
Things to grab in Fairbanks yet
- In room 106 a charge controller for IS2 snow site
- Drill
- Pressure transducer 2 desiccant holder.
Need to submit a PR
- TL-IS2 Snow Stand 10ft pipe
- 3/4 in x 10 ft pipe
Nome Conex Instrument Inventory (May 2022 Edition)
- Left 2 HMP155s in Nome Conex
- Left 1 SR50A in Nome Conex
- Left 1 BP Sensor in Nome Conex
- Left 2 anemometers in Nome Conext
Older Note to follow up on: Teller bottom 2022-05-20
- Problem files
- Micromet110.dat
- Mm112
Teller IS2 Snow
- Need a base plate for 4x4 to keep it from sinking further into muck. That turns out to be the source/reason for the lean.
- Limited Lean 5/22/22 by pounding in rebar with guy wire anchor. Could use rebar cap from storage for it (or from Fairbanks)
- Also on 5/22/22: Verified voltage of solar panel and battery. Charge controller needs replacement
Teller 47
- Guy wire off again creek side
- Baud rate on md485 set to 9600. I always forget so might need to adjust serial port speed before collecting here
- Should really buy a couple of the rs232 cables for the cr6 cas sites
- Should look at pressure data here and compare to teller bottom.
- There are flies in the vent and it should be replaced
- I think we have a baby oil in conex for fall 2022 geonor.
Teller 47 Snow
- Vertical pipe bent a bit over the winter.
Teller Top
- Was going to disconnect and reconnect wiring for HMP155 to see if the weak connection is not the sensor.
- might also try leaving sensor turned on for longer in program (a to do for when CNR4 returns recalibrated)
- Musk Ox within 50 meters of station prevented a visit.
Snow Stand Improvements
- Shipped out in March parts to add a snow depth side diagonal support (just need to buy the pipe).
- Teller 47 snow
- KG-IS5 snow
- Teller IS2 2x
- Should also add back side guy wires to:
- Teller IS2 2x
- Teller 47 snow
- KG-IS5 Snow 2x
Proposed Itinerary
Day 1
- Arrive on evening flight
- Pick up Truck.
- Grocery for perishables and local snacks
- Swing through campus and look at the radio base station antenna
- if weather cooperative / time allows visit anvil otherwise squeeze in early in trip.
Day 2
- Drive to Teller 27
- Gage the Creek
- Download data from all sites at bottom
- Replace radiometer at Teller Bottom
- Replace snow transducers on reachable systems
- level tipping bucket
- Teller Bottom Soil Moisture sensor need a bit of attention. No SDI 12 action.
- Buy and bring out a short step ladder for Teller Bottom CNR4
- Teller IS2 charge controller doesn't look to be working (confirmed looking at March data download).
- Teller sw could use one serial cable
Day 3
- Visit Kougarok sites
- Replace pressure sensor at met station
- m64 met: relevel cnr4 & tipping bucket
- Snipped the pressure vent tube but thinking I should return with something more. Like pvc pipe going to ground so there is even less chance of clogging. Like could add the T sections of drill holes in pipe for venting
- Kg is5 snow
- Replace battery box lid
- Could use a sticky hook to hold serial cables up inside these boxes
- KG South Transect Snow
- All good here nothing to change.
Day 4
- Drive to Teller 47 site
- download data
- dump precip bucket
- need baby oil
- level radiometer
- (ordered a replacement SR50A for the willows site. Will need to deploy this trip)
- Drive to teller top
- download data
- HMP155 cable, try redoing the connections inside the instrument box.
- replace CNR4
Day 5
- Council
- download data at grid and level tipping bucket
- disconnect radio?
- check battery voltage in 21/22 winter.
- Visit Skookum and check out antenna / radio
Day 6
- Wrap up loose ends in town
- Return home on morning flight