Sept 2008 Field Trip - Emily and Ken
This is a to do list written by Emily and Ken detailing work to be done on the Sept 4-11 field trip. Helicopter is available approximately Sept 5-7 and we extended it until we are finished (8-10). We will visit West Kuparuk and Bullen/Foothills sites, along with Put River, Imnaviat Basin, Upper Kuparuk for stream gaging, so bring waders and rubber boots. Remember to make reservations at Toolik (& bring your own sleeping bag/sheets/blankets/pillow)
NSF Sites Notes from Bob (Emily and Rob can take care of these NSF sites on the trip up to Prudhoe).
Note: Sites are grouped by area. Ken add stations that need conduit and bear fencing.
Contents
- 1 Day 0, after drive to Toolik
- 2 Day 1 & 2 West of Dalton Highway (White Hills Area) helicopter sites
- 3 Day 3 (Bullen Area/Kavik Area) helicopter sites
- 4 Day 4 & 5 (Mountain Sites) helicopter sites
- 5 Other TO DO things not helicopter related
- 6 Emily and Rob head up to Deadhorse and gage the Put River Sept 6-7
- 7 Imnaviat Flume
- 8 Upper Kuparuk
- 9 Toolik snow sensor test site
Day 0, after drive to Toolik
1. SagRiverDOT:
- Troubleshoot network at base station
Day 1 & 2 West of Dalton Highway (White Hills Area) helicopter sites
1. West Kuparuk met:
- Troubleshoot station
- Install SR50
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
2. DFM4 NW Kuparuk Met DFM4 :
- Add Electric Fence
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
- Replace SR50. Measure old distance to ground and then measure new dist. after installation.
- Check or Replace Anemometer. Bring spare cable and spare anemometer. Wind speed/direction are 0 since 7/17.
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
- trim vegetation
- Add bark chips
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
- trim vegetation
- Replace SR50. Measure old distance to ground and then measure new dist. after installation.
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
Day 3 (Bullen Area/Kavik Area) helicopter sites
- Check (or replace) net radiometer - readings went bad after we left the site
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
7. DBM8 Bullen Met DBM8
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
8. DBM4 Sag-Ivi Met DBM4:
- Add E-Fence
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
9. DBM5 Upper Kad Met DBM5:
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
- Add E-Fence???
10. DBM6 Kavik Met:
- Add bark chips, trim vegetation
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
Day 4 & 5 (Mountain Sites) helicopter sites
11. DBR2 Ribdon Repeater DBR2 Troubleshooting
- Needs HMP45C
- Needs YSIx3
- Add conduit
12. DBM3 Juniper Met DBM3
- North fence needs another post,
- solar panel wires are exposed, needs "plates" or other protection
- install conduit
- Swap HMP45C
- Add bark chips, trim vegetation (if needed)
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
13. DBM1 Accomplishment Cr Met
- Swap HMP45C
- install conduit if time permits
- install solar panel plate (larger size)
- Add bark chips, trim vegetation (if needed)
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
14. DBM2 Ribdon Cr Met DBM2
- Swap HMP45C
- install conduit
- Add bark chips, trim vegetation (if needed)
- Measure distance from ground to snow sensor
- Take photos of site and snow sensor area
Emily and Rob head up to Deadhorse and gage the Put River Sept 6-7
- Remember to check NSF Sites Notes from Bob
- Install a new larger solar panel and battery
- Gage the site
- repairs to wingwalls as needed
- See NSF Sites Notes from Bob
Upper Kuparuk
- Gage the site
- See NSF Sites Notes from Bob
Toolik snow sensor test site
- Toolik Geonor T200B precip gauge site prep
- select site location
- need 120VAC power
- install concrete base block
- dig hole for about 6CF concrete
- prepare template for 4 bolts, 225cm apart
- mix and place concrete
- set bolts in place; orient N-S and E-W, leave 6" above surface
- protect from elements etc. until set
- sensor to be installed later...
- select site location
- Install SR50 snow sensor
- SR50's, wood chips, etc.
- Mounting equipment
- datalogger
- hmp45c/anememometer?
- wood chips
- Battery, solar panel, charge controller ?
- radio/antennae?